S880947 |
12/30/2021 |
SW - Deficient BMP Implementation |
1. The discharger failed to minimize or prevent pollutants in storm water discharges through the use of controls, structures, and management practices. 2. The discharger failed to provide adequate sediment and erosion controls BMPs throughout the site during a qualifying predicted rain event. |
Violation |
N |
Inspection |
4415 Alamo Street |
S539668 |
2009-0009-DWQ |
Y |
S871003 |
09/02/2019 |
SW - Late Report |
Failure to submit 2018 - 2019 Annual Report by due date |
Violation |
N |
Report |
The Galleria Garden Grove |
S502715 |
2009-0009-DWQ |
Y |
S880950 |
12/30/2021 |
SW - Effluent |
The discharger failed to comply with the Risk Level 2 dischargers that are subject to a turbidity NAL of 250 NTU. |
Violation |
N |
Inspection |
4415 Alamo Street |
S539668 |
2009-0009-DWQ |
N |
S887703 |
12/21/2023 |
SW - Deficient BMP Implementation |
? The discharger failed to minimize or prevent pollutants in stormwater discharges through the use of controls, structures, and management practices that achieve BAT for toxic and non-conventional pollutants and BCT for conventional pollutants. ? The discharger failed to cover and berm loose stockpiled construction materials that were not actively being used (i.e., soil, spoils, aggregate, fly-ash, stucco, hydrated lime, etc.). ? The discharger failed to ensure the effectiveness of existing BMPs to reduce or prevent pollutants in stormwater discharges. ? The discharger failed to provide effective soil cover for inactive areas and all finished slopes ? The discharger failed to establish and maintain effective perimeter controls and stabilize all construction entrances and exits to sufficiently control erosion and sediment discharges from the site. ? The discharger failed to effectively manage all run-on, all runoff within the site, and all runoff that discharges off the site. Run-on from off-site shall be directed away from all disturbed areas or shall collectively be in compliance with the effluent limitations in this General Permit. ? The discharger failed to implement good site management ?housekeeping?. |
Violation |
N |
Inspection |
4415 Alamo Street |
S539668 |
2009-0009-DWQ |
Y |
S880949 |
12/30/2021 |
SW - Incomplete/Insufficient SWPPP |
1.The SWPPP (in SMARTS) did not include a list of names of all contractors, subcontractors, and individuals who will be directed by the QSP. 2. The discharge failed to upload a Post Construction BMP Plan. T 3. The discharger failed to provided BMP weekly, pre-storm, during -storm, and post-storm inspection reports as requested by Staff on December 30, 2021. 4. The discharger failed to provide copies of the REAPs as requested by Staff on December 30, 2021. 5. The discharger failed to provided Water Qual |
Violation |
N |
Inspection |
4415 Alamo Street |
S539668 |
2009-0009-DWQ |
N |
S880502 |
09/01/2021 |
SW - Late Report |
Failure to submit required Annual Report 2021 |
Violation |
N |
Report |
The Village at Burlingame |
S520796 |
2009-0009-DWQ |
Y |