Party ID Party Name Party Classification Mailing Address Work Phone Email/Website
610235 DV Natural Resources Privately-Owned Business 192 Summerfield Court Suite 203 Roanoke, VA 24019 None None
  
  
  
  
Expand/Contract Related Places
Related Places
Place ID Place Name County Region Place Type Relationship to Party Relationship Start Date Relationship End Date
210392 Briggs Mine Project Inyo 6B Metal Mining None None None
Total Related Places: 1
  
  
  
  
Expand/Contract Related Parties
Related Parties
Party ID Party Name Party Type Role/Relationship Relationship Start Date Relationship End Date Classification
610236 Art Fisher Person Employee 06/15/2020 None None
Total Related Parties: 1
  
  
  
  
Expand/Contract Regulatory Measures
Regulatory Measures (non-enforcement)
Reg. Measure ID Regulatory Measure Type Region WDID Status Program Order No. RM Effective Date RM Termination Date Relationship Relationship Start Date Relationship End Date Amended?
438638 WDR 6V 6B149411001 Active LNDISPOTH R6V-2020-0031 05/06/2020 None Discharger 06/15/2020 None N
Total Regulatory Measures: 1
  
  
  
  
Expand/Contract Violations
Violations within the past five years
Violation ID Occurrence Date Violation Type Violation Description(-) Violation Status Priority Source Facility Name Violated Reg. Meas. ID Violated Reg. Meas. Order No. Linked to Enf.
1087911 01/30/2021 Deficient Reporting The 2020 Annual Monitoring Report was due on 01/30/2021 but was not turned in. 52 days late as of 03/23/2021. Violates Board Order R6V-2020-0031 MRP IV.A. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1087915 11/04/2020 Deficient Reporting (1) Wells MW-2B, MW-3, MW-4, MW-5, and MW-6 were not sampled for all Quarterly Monitoring Parameters during the 4th Quarter 2020 monitoring period. Violates Board Order R6V-2020-0031 MRP I.A. Attachment A (2) The Pregnant Pond - Surface Impoundment was not sampled for all Quarterly Monitoring Parameters during the 4th Quarter 2020 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. Attachment A (3) The Make Up Pond Surface Impoundment was not sampled during the 4th Quarter 2020 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.1. (4) Surface Impoundment sludge was not sampled during the 4th Quarter 2020 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. Attachment A Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1100918 10/11/2021 Groundwater Exceeded WQPS of Iron, Mercury, and WAD Cyanide during the 4th Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP I.C.1. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1104492 04/30/2022 Deficient Reporting (1) Groundwater Elevation Data was not included in the 1st Quarter 2022 report and the resulting maps illustrating groundwater elevation, direction, velocity, and isocontours are also missing. Violates Board Order R6V-2020-0031 MRP IV.1.d. (2) Copies of field monitoring and well sampling data sheets were not included in the 1st Quarter 2022 report. Violates Board Order R6V-2020-0031 MRP IV.1.h. (3) The 1st Quarter 2022 report is missing a letter transmitting the essential points of each report, including a discussion of any violations found since the last report was submitted and describing actions taken or planned for correcting those violations. Violates Board Order R6V-2020-0031 MRP IV.A.1.J. (4) Surface Impoundment sludge was not sampled during the 1st Quarter 2022 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. ¿ Attachment A (5) Incomplete EDF Laboratory data uploaded to Geotracker during the 1st Quarter 2022 monitoring period. Violates Board Order R6V-2020-0031 MRP IV.A. (6) Wetland Wells Piezometer Data missing during the 1st Quarter 2022 Violates Board Order R6V-2020-0031 MRP II.F. (7) Barren pond and Detoxification Pond not sampled or reported as dry during the 2022 1st Quarter monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.1 Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1089786 10/30/2020 Order Conditions The Discharger failed to submit a separate Financial Assurance Instrument providing adequate funding for closure activities by October 30, 2020. Violates Board Order No. R6V-2020-0031, Provisions, Section V.B.1 Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1089790 01/30/2021 Order Conditions The Discharger failed to submit a report indicating the Preliminary Closure and Post-closure Maintenance plan report is in conformance with existing Facility operations by January 30,2021. Violates Board Order No. R6V-2020-0031, Provisions, Section IV.D Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1089796 01/25/2021 Deficient Reporting (1) Groundwater Elevation Data was not included in the 1st Quarter 2021 report and the resulting maps illustrating groundwater elevation, direction, velocity, and isocontours are also missing. Violates Board Order R6V-2020-0031 MRP IV.1.d. (2) Copies of field monitoring and well sampling data sheets were not included in the 1st Quarter 2021 report. Violates Board Order R6V-2020-0031 MRP IV.1.h. (3) Surface Impoundment sludge was not sampled during the 1st Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. ¿ Attachment A (4) Missing a letter transmitting the essential points of each report, including a discussion of any violations found since the last report was submitted and describing actions taken or planned for correcting those violations. Violates Board Order R6V-2020-0031 MRP IV.A.1.J. (5) Surface Impoundments were not sampled for all Quarterly Monitoring Parameters during the 1st Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. ¿ Attachment A Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1089797 01/25/2021 Groundwater Exceeded WQPS of Iron and WAD Cyanide during the 1st Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP I.C.1. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1096314 10/29/2021 Deficient Reporting (1) Water quality graphs are missing an identification that a sample exceeded the concentration limit by a significant amount during the 3rd Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP IV.1.a.1.b. (2) Groundwater Elevation Data was not included in the 3rd Quarter 2021 report and the resulting maps illustrating groundwater elevation, direction, velocity, and isocontours are also missing. Violates Board Order R6V-2020-0031 MRP IV.1.d. (3) Copies of field monitoring and well sampling data sheets were not included in the 3rd Quarter 2021 report. Violates Board Order R6V-2020-0031 MRP IV.1.h. (4) The 3rd Quarter 2021 report is missing a letter transmitting the essential points of each report, including a discussion of any violations found since the last report was submitted and describing actions taken or planned for correcting those violations. Violates Board Order R6V-2020-0031 MRP IV.A.1.J. (5) Surface Impoundment sludge was not sampled during the 3rd Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. ¿ Attachment A (6) Surface Impoundments were not sampled for all Quarterly Monitoring Parameters during the 3rd Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. ¿ Attachment A Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1100919 02/09/2022 Deficient Reporting (1) Missing a list of all monitoring point/monitoring parameter pairs (pairs), by medium, which have exhibited a verified measurably significant increase. Violates Board Order R6V-2020-0031 MRP IV.A.2.c. (2) Missing four maps, for each quarter, that show groundwater elevation isocontours, monitoring points, surface trace for each waste management unit, observation stations, and the surface trace of the facility¿s point of compliance. Violates Board Order R6V-2020-0031 MRP IV.A.2.d. (3) Missing graphical data for all constituents during the 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP IV.A.2.e. (4) Missing calibration methods of any meters used for field parameters. Violates Board Order R6V-2020-0031 MRP IV.A.2.f. (5) Missing an evaluation of the effectiveness of the groundwater and unsaturated zone monitoring programs. Violates Board Order R6V-2020-0031 MRP IV.A.2.g. (6) Missing a brief summary of dates of any operational problems and maintenance activities. Violates Board Order R6V-2020-0031 MRP IV.A.2.h. (7) Missing the compliance record and corrective actions taken or planned. Violates Board Order R6V-2020-0031 MRP IV.A.2.i. (8) Missing Financial Assurance. Violates Board Order R6V-2020-0031 MRP IV.A.2.j. and k. (9) Missing a review of the preliminary closure plan and corrective action plan for all known or reasonably foreseeable releases. Violates Board Order R6V-2020-0031 MRP IV.A.2.l. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1089788 10/30/2020 Order Conditions The Discharger failed to submit a separate Financial Assurance Instrument providing adequate funding for post-closure monitoring and maintenance activities by October 30, 2020. Violates Board Order No. R6V-2020-0031, Provisions, Section V.B.2 Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1100917 01/31/2022 Deficient Reporting (1) Nitrate was not sampled in all wells during the 4th Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP I.B. - Attachment A (2) Monitoring well MW-5 was not sampled during the 4th Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP I.D. (3) Groundwater Elevation Data was not included in the 4th Quarter 2021 report and the resulting maps illustrating groundwater elevation, direction, velocity, and isocontours are also missing. Violates Board Order R6V-2020-0031 MRP IV.1.d. (4) Copies of field monitoring and well sampling data sheets were not included in the 4th Quarter 2021 report. Violates Board Order R6V-2020-0031 MRP IV.1.h. (5) The 4th Quarter 2021 report is missing a letter transmitting the essential points of each report, including a discussion of any violations found since the last report was submitted and describing actions taken or planned for correcting those violations. Violates Board Order R6V-2020-0031 MRP IV.A.1.J. (6) Surface Impoundment sludge was not sampled during the 4th Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. ¿ Attachment A Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1104491 02/16/2022 Groundwater Exceeded WQPS of Copper, Iron, Mercury, and WAD Cyanide during the 1st Quarter 2022 monitoring period. Violates Board Order R6V-2020-0031 MRP I.C.1. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1089785 09/01/2020 Order Conditions The Discharger failed to submit a technical report proposing an EMP by September 1, 2020. Violates Board Order No. R6V-2020-0031, Provisions, Section V.A Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1089791 01/30/2021 Order Conditions The Discharger failed to submit a report indicating that the know or reasonably foreseeable release plan is in conformance with existing Facility Conditions by January 30,2021. Violates Board Order No. R6V-2020-0031, Provisions, Section IV.E Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1089789 10/30/2020 Order Conditions The Discharger failed to submit a separate Financial Assurance Instrument providing adequate funding for corrective action of a known and reasonably foreseeable release by October 30, 2020. Violates Board Order No. R6V-2020-0031, Provisions, Section V.B.3 Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1087391 01/31/2021 Deficient Reporting (1) Groundwater Elevation Data was not included in the 2020 Quarter 4 report and the resulting maps illustrating groundwater elevation, direction, velocity, and isocontours are also missing. Violates Board Order R6V-2020-0031 MRP IV.1.d. (2) Copies of field monitoring and well sampling data sheets were not included. Violates Board Order R6V-2020-0031 MRP IV.1.h. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
1087914 11/04/2020 Groundwater Exceeded WQPS of Iron and WAD Cyanide during the 4th Quarter 2020 monitoring period. Violates Board Order R6V-2020-0031 MRP I.C.1. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1096311 04/22/2021 Groundwater Exceeded WQPS of Iron, Mercury, and WAD Cyanide during the 2nd Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP I.C.1. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1089803 10/30/2020 Late Report The 2020 Quarter 3 Monitoring Report was due on 10/30/2020 and was turned in on 12/8/2020. 39 Days Late. Violates Board Order R6V-2020-0031 MRP IV.A. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1089801 09/28/2020 Deficient Reporting (1) Groundwater Elevation Data was not included in the 2020 Quarter 3 report and the resulting maps illustrating groundwater elevation, direction, velocity, and isocontours are also missing. Violates Board Order R6V-2020-0031 MRP IV.1.d. (2) Copies of field monitoring and well sampling data sheets were not included in the 2020 Quarter 3 report. Violates Board Order R6V-2020-0031 MRP IV.1.h. (3) Surface Impoundments were not sampled during the 2020 Quarter 3 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.1. (4) Surface Impoundment sludge was not sampled during the 2020 Quarter 3 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. ¿ Attachment A (5) Missing a letter transmitting the essential points of each report, including a discussion of any violations found since the last report was submitted and describing actions taken or planned for correcting those violations. Violates Board Order R6V-2020-0031 MRP IV.A.1.J. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1096312 07/29/2021 Deficient Reporting (1) Water quality graphs are missing an identification that a sample exceeded the concentration limit by a significant amount during the 2nd Quarter 2021monitoring period. Violates Board Order R6V-2020-0031 MRP IV.1.a.1.b. (2) Groundwater Elevation Data was not included in the 2nd Quarter 2021 report and the resulting maps illustrating groundwater elevation, direction, velocity, and isocontours are also missing. Violates Board Order R6V-2020-0031 MRP IV.1.d. (3) Copies of field monitoring and well sampling data sheets were not included in the 2nd Quarter 2021 report. Violates Board Order R6V-2020-0031 MRP IV.1.h. (4) The 2nd Quarter 2021 report is missing a letter transmitting the essential points of each report, including a discussion of any violations found since the last report was submitted and describing actions taken or planned for correcting those violations. Violates Board Order R6V-2020-0031 MRP IV.A.1.J. (5) Surface Impoundment sludge was not sampled during the 2nd Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.2. ¿ Attachment A (6) Unsaturated Zone monitoring not completed during the 2nd Quarter 2021 monitoring period. Lysimeters equipment malfunctioned. Violates Board Order R6V-2020-0031 MRP II.C. (7) Surface Impoundments were not sampled during the 2nd Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP II.A.1. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1089802 09/28/2020 Groundwater Exceeded WQPS of Iron, Mercury, and WAD Cyanide during the 2020 Quarter 3 monitoring period. Violates Board Order R6V-2020-0031 MRP I.C.1. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1104646 03/31/2022 Order Conditions Exceeded Action Leakage Rates and/or Rapid and Large Leak Rates for West Pregnant Pond and East Pregnant Pond during the 2022 Q1 monitoring period. Violates Board Order R6V-2020-0031 MRP II.B.6. Table 1 Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1096313 07/28/2021 Groundwater Exceeded WQPS of Iron, Mercury, and WAD Cyanide during the 3rd Quarter 2021 monitoring period. Violates Board Order R6V-2020-0031 MRP I.C.1. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 N
1090899 07/30/2020 Late Report The 2020 Annual Storm Water Report was due on 07/30/2020 but was not turned in. Violates Board Order R6V-2020-0031 MRP IV.A.3. Violation N Report Briggs Mine Project 438638 R6V-2020-0031 Y
Report currently showing last five years of violations. Click here to return to viewing one year of violations. Refer to the Interactive Violation Report for more data.
Total Violations: 26
*Click the "(+/-) Violation Description" link to expand and contract the violation description.
  
  
  
  
Expand/Contract Enforcement Actions
Enforcement Actions
Enforcement ID Enforcement Type Enf. Order No. Title Program Effective Date Status
449825 Oral Communication None Oral Com 11/08/2022 for DV Natural Resources LNDISPOTH 11/08/2022 Historical
447847 Staff Enforcement Letter None SEL for DV Natural Resources LNDISPOTH 05/27/2022 Active
447045 Oral Communication None Waste Discharge Requirements 02/17/2022 for DV Natural Resources LNDISPOTH 02/17/2022 Historical
447044 Oral Communication None Oral Com 11/02/2021 for DV Natural Resources LNDISPOTH 11/02/2021 Historical
443513 Staff Enforcement Letter None SEL 03/22/2021 for DV Natural Resources LNDISPOTH 03/22/2021 Active
443255 Notice of Violation None NOV 05/10/2021 for DV Natural Resources LNDISPOTH 05/10/2021 Active
442537 Oral Communication None Oral Com 03/03/2021 for DV Natural Resources LNDISPOTH 03/03/2021 Historical
Total Enforcement Actions: 7
  
  
  
  
Expand/Contract Enforcement Actions
Regulatory Measures linked to Related Parties
Reg. Measure ID Organization Regulatory Measure Type Program Effective Date Status
438638 Art Fisher WDR LNDISPOTH 05/06/2020 Active
Total Regulatory Measures linked to Related Parties: 1
  
  
The current report was generated with data as of: 05/17/2024