Violation ID |
Occurrence Date |
Violation Type |
Violation Description(-) |
Violation Status |
Priority |
Source |
Facility Name |
Violated Reg. Meas. ID |
Violated Reg. Meas. Order No. |
Linked to Enf. |
1101945 |
04/20/2021 |
Groundwater |
The April 2021 samples for nitrate in groundwater wells B and C contained nitrate as nitrogen concentrations of 11 and 14 milligrams per liter, respectively. These concentrations are greater than the primary MCL for nitrate as nitrogen of 10 milligrams per liter. Causing a concentration of a chemical constituent in the receiving water to be in excess of the maximum contaminant levels constitutes a violation of Board Order No. R6V-2004 00018 requirement I. Discharge Specifications, B. Receiving Water Limitations, 5. (page 4 of the order). |
Violation |
N |
Report |
Hilton Creek CSD Package STP |
133595 |
04-018 |
Y |
1080314 |
07/13/2020 |
Deficient Monitoring |
(1) Violation Description: Missing Flow Monitoring Data for the 2020 Quarter 2 monitoring period. Violates Board Order R6V-2004-0018 MRP I.A. (2) Violation Description: Missing Groundwater Monitoring Semi-annual Parameters for the 2020 Quarter 2 monitoring period. Violates Board Order R6V-2004-0018 MRP I.C. |
Violation |
N |
Report |
Hilton Creek CSD Package STP |
133595 |
04-018 |
Y |
1067878 |
07/15/2019 |
Late Report |
The 2019 Quarter 2 Monitoring Report was due on 7/15/2019 and was turned in on 8/27/2020. 409 Days Late. Violates Board Order R6V-2004-0018 MRP II.B. |
Violation |
N |
Report |
Hilton Creek CSD Package STP |
133595 |
04-018 |
N |
1080311 |
08/14/2019 |
Deficient Reporting |
(1) Missing Flow Monitoring. Violates Board Order R6V-2004-0018 MRP I.A.1. (2) Missing percolation pond freeboard or an indication that the pond is empty. Violates Board Order R6V-2004-0018 MRP I.A.2. |
Violation |
N |
Report |
Hilton Creek CSD Package STP |
133595 |
04-018 |
N |
1080315 |
04/15/2020 |
Late Report |
The 2020 Quarter 1 Monitoring Report was due no 4/15/2020 but was not turned in. Violates Board Order R6V-2004-0018 MRP II.B. |
Violation |
N |
Report |
Hilton Creek CSD Package STP |
133595 |
04-018 |
N |
1067879 |
10/15/2019 |
Late Report |
The 2019 Quarter 3 Monitoring Report was due on 10/15/2019 and was turned in on 8/27/2020. 317 Days Late. Violates Board Order R6V-2004-0018 MRP II.B. |
Violation |
N |
Report |
Hilton Creek CSD Package STP |
133595 |
04-018 |
N |
1080313 |
01/15/2020 |
Late Report |
The 2019 Quarter 4 Monitoring Report was due on 1/15/2020 and was turned in on 8/27/2020. 225 Days Late. Violates Board Order R6V-2004-0018 MRP II.B. |
Violation |
N |
Report |
Hilton Creek CSD Package STP |
133595 |
04-018 |
N |
Report currently showing last five years of violations. Click here to return to viewing one year of violations. Refer to the Interactive Violation Report for more data.
|