We were not able to collect the semi-annual samples at William E. Warne powerpla
Violation
N
eSMR
William E Warne Power Plant
446992
R4-2022-0237
N
1153745
02/18/2026
Deficient Monitoring
We were not able to collect the semi-annual samples at William E. Warne powerpla
Violation
N
eSMR
William E Warne Power Plant
446992
R4-2022-0237
N
1153744
02/18/2026
Deficient Monitoring
We were not able to collect the semi-annual samples at William E. Warne powerpla
Violation
N
eSMR
William E Warne Power Plant
446992
R4-2022-0237
N
1153743
02/18/2026
Deficient Monitoring
We were not able to collect the semi-annual samples at William E. Warne powerpla
Violation
N
eSMR
William E Warne Power Plant
446992
R4-2022-0237
N
1153742
03/18/2026
CAT1
Biochemical Oxygen Demand (BOD) (5-day @ 20 Deg. C) Daily Maximum limit is 10 mg
Violation
N
eSMR
William E Warne Power Plant
446992
R4-2022-0237
N
Report defaults to display violations within the last year. Click here to see last five years of violations. Refer to the Interactive Violation Report for more data.
Total Violations: 5
*Click the "(+/-) Violation Description" link to expand and contract the violation description.
Total Regulatory Measures linked to Related Parties: 4
The current report was generated with data as of: 10/22/2026
Regional Boards are in the process of entering backlogged data.
As a result, data may be incomplete.