Violation ID |
Occurrence Date |
Violation Type |
Violation Description(-) |
Violation Status |
Priority |
Source |
Facility Name |
Violated Reg. Meas. ID |
Violated Reg. Meas. Order No. |
Linked to Enf. |
1109992 |
07/01/2021 |
Late Report |
May 2021 SMR due 01 July 2021, not submitted (502 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109974 |
12/01/2020 |
Late Report |
October 2020 SMR due 01 December 2020, not submitted (714 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110003 |
06/01/2022 |
Late Report |
April 2022 SMR due 01 June 2022, not submitted (167 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109999 |
02/01/2022 |
Late Report |
December 2021 SMR due 01 February 2022, not submitted (287 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110001 |
04/01/2022 |
Late Report |
February 2022 SMR due 01 April 2022, not submitted (228 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109892 |
06/30/2019 |
Deficient Monitoring |
June 2019 SMR missing continuous Flow from effluent monitoring (30x) and Monthly BOD, TDS, Nitrate (as N), and TKN from pond monitoring (1x). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109990 |
05/01/2021 |
Late Report |
March 2021 SMR due 01 May 2021, not submitted (563 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109998 |
01/01/2022 |
Late Report |
November 2021 SMR due 01 January 2022, not submitted (318 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109961 |
04/01/2020 |
Late Report |
February 2020 SMR due 01 April 2020, not submitted (958 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109993 |
08/01/2021 |
Late Report |
June 2021 SMR due 01 August 2021, not submitted (471 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109997 |
12/01/2021 |
Late Report |
October 2021 SMR due 01 December 2021, not submitted (349 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109891 |
06/30/2019 |
Deficient Reporting |
June 2019 SMR missing signature and certification statement. |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109978 |
02/01/2021 |
Late Report |
December 2020 SMR due 01 February 2021, not submitted (652 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109977 |
11/30/2020 |
Deficient Monitoring |
November 2020 SMR missing continuous Flow from effluent monitoring (30x) and Monthly BOD, TDS, Nitrate (as N), and TKN from pond monitoring (1x). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109893 |
08/01/2019 |
Late Report |
July 2019 SMR due 01 September 2019, not submitted (1166 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109958 |
12/31/2019 |
Deficient Reporting |
December 2019 SMR missing signature and certification statement. |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109988 |
03/01/2021 |
Late Report |
January 2021 SMR due 01 March 2021, not submitted (624 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109959 |
12/31/2019 |
Deficient Monitoring |
December 2019 SMR missing continuous Flow from effluent monitoring (31x) and Monthly BOD, TDS, Nitrate (as N), and TKN from pond monitoring (1x). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109890 |
05/31/2019 |
Deficient Monitoring |
May 2019 SMR missing continuous Flow from effluent monitoring (31x) and Monthly BOD, TDS, Nitrate (as N), and TKN from pond monitoring (1x). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109956 |
11/30/2019 |
Deficient Reporting |
November 2019 SMR missing signature and certification statement. |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110005 |
08/01/2022 |
Late Report |
June 2022 SMR due 01 August 2022, not submitted (106 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109994 |
09/01/2021 |
Late Report |
July 2021 SMR due 01 September 2021, not submitted (440 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109995 |
10/01/2021 |
Late Report |
August 2021 SMR due 01 October 2021, not submitted (410 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109895 |
08/31/2019 |
Deficient Reporting |
August 2019 SMR missing signature and certification statement. |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109970 |
08/31/2020 |
Deficient Reporting |
August 2020 SMR missing signature and certification statement. |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109966 |
08/01/2020 |
Late Report |
June 2020 SMR due 01 August 2020, not submitted (836 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109896 |
08/31/2019 |
Deficient Monitoring |
August 2019 SMR missing continuous Flow from effluent monitoring (31x) and Monthly BOD, TDS, Nitrate (as N), and TKN from pond monitoring (1x). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109962 |
05/01/2020 |
Late Report |
March 2020 SMR due 01 May 2020, not submitted (928 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110006 |
09/01/2022 |
Late Report |
July 2022 SMR due 01 September 2022, not submitted (75 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109963 |
06/01/2020 |
Late Report |
April 2020 SMR due 01 June 2020, not submitted (897 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110007 |
10/01/2022 |
Late Report |
August 2022 SMR due 01 October 2022, not submitted (45 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110004 |
07/01/2022 |
Late Report |
May 2022 SMR due 01 July 2022, not submitted (137 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109889 |
05/31/2019 |
Deficient Reporting |
May 2019 SMR missing signature and certification statement. |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109975 |
11/30/2020 |
Deficient Reporting |
November 2020 SMR missing signature and certification statement. |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109897 |
11/01/2019 |
Late Report |
September 2019 SMR due 01 November 2019, not submitted (1105 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109955 |
12/01/2019 |
Late Report |
October 2019 SMR due 01 December 2019, not submitted (1080 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109972 |
08/31/2020 |
Deficient Monitoring |
August 2020 SMR missing continuous Flow from effluent monitoring (31x) and Monthly BOD, TDS, Nitrate (as N), and TKN from pond monitoring (1x). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109957 |
11/30/2019 |
Deficient Monitoring |
November 2019 SMR missing continuous Flow from effluent monitoring (30x) and Monthly BOD, TDS, Nitrate (as N), and TKN from pond monitoring (1x). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109991 |
06/01/2021 |
Late Report |
April 2021 SMR due 01 June 2021, not submitted (532 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110008 |
11/01/2022 |
Late Report |
September 2022 SMR due 01 November 2022, not submitted (14 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109989 |
04/01/2021 |
Late Report |
February 2021 SMR due 01 April 2021, not submitted (593 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110002 |
05/01/2022 |
Late Report |
March 2022 SMR due 01 May 2022, not submitted (198 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109960 |
03/01/2020 |
Late Report |
January 2020 SMR due 01 March 2020, not submitted (989 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109996 |
11/01/2021 |
Late Report |
September 2021 SMR due 01 November 2021, not submitted (379 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109967 |
09/01/2020 |
Late Report |
July 2020 SMR due 01 September 2020, not submitted (805 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109964 |
07/01/2020 |
Late Report |
May 2020 SMR due 01 July 2020, not submitted (867 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1109973 |
11/01/2020 |
Late Report |
September 2020 SMR due 01 November 2020, not submitted (744 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
1110000 |
03/01/2022 |
Late Report |
January 2022 SMR due 01 March 2022, not submitted (259 days late). |
Violation |
None |
Report |
Exeter-Ivanhoe Citrus Association |
144163 |
85-106 |
N |
Report currently showing last five years of violations. Click here to return to viewing one year of violations. Refer to the Interactive Violation Report for more data.
|