| Violation ID |
Occurrence Date |
Violation Type |
Violation Description(-) |
Violation Status |
Priority |
Source |
Facility Name |
Violated Reg. Meas. ID |
Violated Reg. Meas. Order No. |
Linked to Enf. |
| S896264 |
09/02/2025 |
SW - Failure to Obtain Permit |
Failure to obtain coverage under the 2022 CGP by 09/01/2025. |
Violation |
N |
Internal Report |
Lancaster Apartments |
S551096 |
2009-0009-DWQ |
Y |
| S896191 |
09/02/2025 |
SW - Failure to Obtain Permit |
Failure to obtain coverage under the 2022 CGP by 09/01/2025. |
Violation |
N |
Internal Report |
Palo Verde Tract 32279 and 33336 |
S547626 |
2009-0009-DWQ |
Y |
| S895186 |
09/02/2025 |
SW - Failure to Obtain Permit |
Failure to obtain coverage under the 2022 CGP by 09/01/2025. |
Violation |
N |
Internal Report |
Valley Villas |
S551374 |
2009-0009-DWQ |
Y |
| S895169 |
09/02/2025 |
SW - Failure to Obtain Permit |
Failure to obtain coverage under the 2022 CGP by 09/01/2025. |
Violation |
N |
Internal Report |
Collins Drive |
S550599 |
2009-0009-DWQ |
Y |
| S894219 |
09/02/2025 |
SW - Failure to Obtain Permit |
Failure to obtain coverage under the 2022 CGP by 09/01/2025. |
Violation |
N |
Internal Report |
Tract 60259 Park Place |
S544607 |
2009-0009-DWQ |
Y |
| S891637 |
06/23/2025 |
SW - Deficient BMP Implementation |
? Sediment track-out was observed on adjacent streets. ? Stabilized entrance/exit locations at Goodenough Road and B Street require additional BMPs. ? Perimeter controls were found to be inadequate around the entire project boundary. ? Visible dust emissions were observed in the air due to grading and earth-moving activities. |
Violation |
N |
Inspection |
Fillmore Tract 5422 Creekside |
S531393 |
2009-0009-DWQ |
Y |
| S886060 |
09/28/2023 |
SW - Late Report |
Failed to submit the 2022-2023 Annual Report |
Violation |
N |
Inspection |
Tract 5655 Lots 2 through 4 |
S528251 |
2009-0009-DWQ |
N |
| S883554 |
09/02/2022 |
SW - Late Report |
Failure to submit 2021-2022 Annual Report by September 1, 2022 due date. |
Violation |
N |
Report |
Campanile |
S546156 |
2009-0009-DWQ |
Y |
| S880938 |
12/30/2021 |
SW - Incomplete/Insufficient SWPPP |
SWPPP Violations: 1. The discharger failed to update the Risk Assessment for the project when the date for construction completion changed; the construction end date identified in SMARTS is December 31, 2021. A new Risk Assessment is required for the revised construction end date; the permittee needs to complete a revised Risk Assessment. 2. The SWPPP (in SMARTS) did not include the list of names of all contractors, subcontractors, and individuals who will be directed by the QSP. 3. The discharger failed to upload a Post-Construction BMP Plan. T 4. The discharger failed to submit the 2020-2021 Annual Report due on September 1, 2021. 5. The discharger failed to provide BMP weekly, pre-storm, during-storm, and post-storm inspection reports when requested by Staff on December 30, 2021. |
Violation |
N |
Inspection |
Tract 5984 |
S516980 |
2009-0009-DWQ |
Y |
| S880937 |
12/30/2021 |
SW - Deficient BMP Implementation |
BMP Violations: 1. The discharger failed to minimize or prevent pollutants in stormwater discharges through the use of controls, structures, and best management practices. 2. The discharger failed to provide adequate sediment and erosion control BMPs throughout the Site during a forecasted qualifying storm event (QSE). 3. Poor housekeeping was observed. Trash and concrete/stucco piles, debris, and spilled waste materials were observed throughout the Site without proper BMP measures in place. |
Violation |
N |
Inspection |
Tract 5984 |
S516980 |
2009-0009-DWQ |
Y |
|
Report currently showing last five years of violations. Click here to return to viewing one year of violations. Refer to the Interactive Violation Report for more data.
|