Violation ID |
Occurrence Date |
Violation Type |
Violation Description(-) |
Violation Status |
Priority |
Source |
Facility Name |
Violated Reg. Meas. ID |
Violated Reg. Meas. Order No. |
Linked to Enf. |
1125960 |
02/12/2024 |
CAT2 |
Chromium (VI) Dissolved Daily Maximum limit is 16 ug/L and reported value was 19 ug/L at EFF-001. |
Violation |
N |
eSMR |
SPX Marley Cooling Technologies |
429124 |
R5-2019-0018 |
N |
1125295 |
02/12/2024 |
CAT2 |
Chromium (VI) Dissolved Daily Maximum limit is 16 ug/L and reported value was 19 ug/L at EFF-001. |
Violation |
N |
eSMR |
SPX Marley Cooling Technologies |
429124 |
R5-2019-0018 |
N |
1121282 |
09/21/2023 |
Order Conditions |
During the site inspection, Water Board staff was informed by the Discharger that the facility was currently undergoing a plant expansion to add another cooking line to the plant and that flows would increase to approximately 83,000 gallons per day. This expansion is because the Darling Ingredients Fresno plant will be closed by the end of 2023. Because Water Board staff was not notified of proposed expansion the Discharger is in violation of Provision I.12 of the WDRs which states: "As As described in the Standard Provisions, the Discharger shall report promptly to the Central Valley Water Board any material change or proposed change in the character, location, or volume of the discharge.? |
Violation |
N |
Inspection |
Darling Ingredients, Inc. Rendering Plant |
387815 |
R5-2012-0104 |
N |
1121280 |
09/21/2023 |
Order Conditions |
Water Board staff observed liquid waste and solids (waste byproducts) observed in wastewater pond 1A, which is an unlined pond in violation of Discharge Prohibition A.5 of the WDR, which states: ?Discharge of waste at a location or in a manner different from that described in the Findings is prohibited.? |
Violation |
None |
Inspection |
Darling Ingredients, Inc. Rendering Plant |
387815 |
R5-2012-0104 |
Y |
1118689 |
05/31/2023 |
CAT2 |
Chromium (VI) Dissolved Daily Maximum limit is 16 ug/L and reported value was 28 ug/L at EFF-001. |
Violation |
N |
eSMR |
SPX Marley Cooling Technologies |
429124 |
R5-2019-0018 |
N |
1118164 |
05/31/2023 |
CAT2 |
Chromium (VI) Dissolved Monthly Average limit is 16.0 ug/L and reported value was 28.0 ug/L at EFF-001. |
Violation |
N |
eSMR |
SPX Marley Cooling Technologies |
429124 |
R5-2019-0018 |
N |
Report defaults to display violations within the last year. Click here to see last five years of violations. Refer to the Interactive Violation Report for more data.
|