Violation ID |
Occurrence Date |
Violation Type |
Violation Description(-) |
Violation Status |
Priority |
Source |
Facility Name |
Violated Reg. Meas. ID |
Violated Reg. Meas. Order No. |
Linked to Enf. |
1125156 |
02/15/2024 |
Other Codes |
CWC Section 13260(a): for Unauthorized Discharge, failure to submit a complete Report of Waste Discharge |
Violation |
None |
Inspection |
Midway-Sunset Oil Field, A Lease (aka: Sunset Lease) |
401124 |
None |
Y |
1124244 |
02/02/2024 |
Late Report |
Semi-Annual SMR ( MONNPDES ) (Acute Toxicity) report for H2 2023 (2559461) was due on 01-FEB-24 |
Violation |
None |
Report |
Price Canyon Production Facility |
444437 |
R3-2021-0010 |
N |
1102066 |
02/01/2022 |
Order Conditions |
The 2021 Dry Season Biennial Receiving Water report was originally due on 2/1/2022. Please note that the previous biennial receiving water report was submitted in March 2021 (permit due date was 4/1/2021 for the 2020 dry/wet season. Although the new subject Order (effective 7/1/2021) pushed up the schedule by one year, we were not expecting to complete the biennial receiving water sampling until the dry season of 2022. However, upon close review of the updated permit and the online CIWQS schedule, we did see that the 2021 dry season sampling was inadvertently missed and notified the Waterboard via email of this matter on 1/31/2022. |
Violation |
N |
eSMR |
Price Canyon Production Facility |
444437 |
R3-2021-0010 |
N |
1102065 |
02/01/2022 |
Order Conditions |
The 2021 Dry Season Biennial Receiving Water report was originally due on 2/1/2022. Please note that the previous biennial receiving water report was submitted in March 2021 (permit due date was 4/1/2021 for the 2020 dry/wet season. Although the new subject Order (effective 7/1/2021) pushed up the schedule by one year, we were not expecting to complete the biennial receiving water sampling until the dry season of 2022. However, upon close review of the updated permit and the online CIWQS schedule, we did see that the 2021 dry season sampling was inadvertently missed and notified the Waterboard via email of this matter on 1/31/2022. |
Violation |
N |
eSMR |
Price Canyon Production Facility |
444437 |
R3-2021-0010 |
N |
1100639 |
02/02/2022 |
Late Report |
Once Only OneTime ( MONNPDES ) (Rec Wtr 2021 Dry Season) report for 2021/01/01 (2507009) was due on 01-FEB-22 |
Violation |
None |
Report |
Price Canyon Production Facility |
444437 |
R3-2021-0010 |
N |
1099184 |
11/02/2021 |
Late Report |
Semi-Annual SMR ( MONNPDES ) (Chronic Toxicity) report for H2 2021 (2559479) was due on 01-NOV-21 |
Violation |
None |
Report |
Price Canyon Production Facility |
444437 |
R3-2021-0010 |
N |
1096525 |
11/02/2021 |
Late Report |
Quarterly SMR ( MONNPDES ) (Qtrly Constituents ) report for Q3 2021 (2507003) was due on 01-NOV-21 |
Violation |
None |
Report |
Price Canyon Production Facility |
444437 |
R3-2021-0010 |
N |
Report currently showing last five years of violations. Click here to return to viewing one year of violations. Refer to the Interactive Violation Report for more data.
|