Violation ID |
Occurrence Date |
Violation Type |
Violation Description(+) |
Violation Status |
Priority |
Source |
Facility Name |
Violated Reg. Meas. ID |
Violated Reg. Meas. Order No. |
Linked to Enf. |
1118914 |
12/31/2022 |
Late Report |
Processed and discharged on site more than 100,000 gallons of winery wastewater |
Violation |
None |
Report |
Perry Creek Winery |
448885 |
R5-2020-0002 |
N |
1118913 |
02/01/2023 |
Late Report |
No 2022 annual report was received |
Violation |
None |
Report |
Perry Creek Winery |
448885 |
R5-2020-0002 |
N |
1114510 |
02/06/2023 |
Late Report |
Techncial Report required by 8 July 2022 submitted 123 days late. |
Violation |
None |
Report |
Perry Creek Winery |
448885 |
R5-2020-0002 |
N |
1113938 |
01/19/2023 |
Unauthorized Discharge |
During the inspection of the Town Field, including the tailwater control and ret |
Violation |
None |
Inspection |
Ione WWTF |
368758 |
R5-2013-0022 |
N |
1113937 |
01/19/2023 |
Unauthorized Discharge |
During the inspection of the Town Field, including the tailwater control and ret |
Violation |
None |
Inspection |
Ione WWTF |
368758 |
R5-2013-0022 |
N |
1113936 |
01/19/2023 |
Unauthorized Discharge |
During the inspection of the Town Field, including the tailwater control and ret |
Violation |
None |
Inspection |
Ione WWTF |
368758 |
R5-2013-0022 |
N |
1113935 |
01/19/2023 |
Unauthorized Discharge |
During the inspection of the Town Field, including the tailwater control and ret |
Violation |
None |
Inspection |
Ione WWTF |
368758 |
R5-2013-0022 |
N |
1113934 |
01/19/2023 |
Unauthorized Discharge |
During the inspection of the Town Field, including the tailwater control and ret |
Violation |
None |
Inspection |
Ione WWTF |
368758 |
R5-2013-0022 |
N |
1113933 |
01/19/2023 |
Unauthorized Discharge |
During the inspection of the Town Field, including the tailwater control and ret |
Violation |
None |
Inspection |
Ione WWTF |
368758 |
R5-2013-0022 |
N |
1113932 |
01/19/2023 |
Unauthorized Discharge |
During the inspection of the Town Field, including the tailwater control and ret |
Violation |
None |
Inspection |
Ione WWTF |
368758 |
R5-2013-0022 |
N |
1112174 |
01/11/2023 |
Unauthorized Discharge |
Regional Board staff reached out to the Perry Creek Winery but received no respo |
Violation |
None |
Complaint |
Perry Creek Winery |
448885 |
R5-2020-0002 |
N |
1112173 |
01/11/2023 |
Unauthorized Discharge |
Regional Board staff reached out to the Perry Creek Winery but received no respo |
Violation |
None |
Complaint |
Perry Creek Winery |
448885 |
R5-2020-0002 |
N |
1112172 |
01/11/2023 |
Unauthorized Discharge |
Regional Board staff reached out to the Perry Creek Winery but received no respo |
Violation |
None |
Complaint |
Perry Creek Winery |
448885 |
R5-2020-0002 |
N |
1112171 |
01/11/2023 |
Unauthorized Discharge |
Regional Board staff reached out to the Perry Creek Winery but received no respo |
Violation |
None |
Complaint |
Perry Creek Winery |
448885 |
R5-2020-0002 |
N |
1106653 |
07/22/2022 |
Unauthorized Discharge |
On 23 July 2022 Board staff received a Spill Report #22-4181 from the Office of |
Violation |
None |
Report |
CDCR - Mule Creek State Prison WWTP |
368766 |
R5-2015-0129 |
N |
1089763 |
03/30/2021 |
Order Conditions |
1. It does not appear disinfection has been added to the treatment train as requ |
Violation |
N |
Inspection |
Ione WWTF |
368758 |
R5-2013-0022 |
N |
Report currently showing last five years of violations. Click here to return to viewing one year of violations. Refer to the Interactive Violation Report for more data.
|