Violation ID |
Occurrence Date |
Violation Type |
Violation Description(+) |
Violation Status |
Priority |
Source |
Facility Name |
Violated Reg. Meas. ID |
Violated Reg. Meas. Order No. |
Linked to Enf. |
1145347 |
06/30/2025 |
Deficient Monitoring |
Oil and Grease was not sampled during the January - June 2025 period. |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141799 |
02/20/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141796 |
02/19/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141802 |
02/18/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141801 |
02/17/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141800 |
02/16/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141798 |
02/15/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141795 |
02/14/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141794 |
02/13/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141793 |
02/12/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1141797 |
02/11/2025 |
Deficient Monitoring |
SPI failed to realize the flow meter was not downloading data. Did not get a dai |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1147204 |
02/03/2025 |
Order Conditions |
The Discharger failed to maintain a freeboard of 2 feet or greater in the Fire P |
Violation |
None |
Report |
SPI Burney Division |
436971 |
R5-2020-0017 |
Y |
1147192 |
02/03/2025 |
Other Codes |
The Discharger violated California Water Code (CWC) Section 13376. Between 3 Feb |
Violation |
N |
Report |
SPI Burney Division |
436971 |
R5-2020-0017 |
Y |
1147203 |
02/03/2025 |
Unauthorized Discharge |
The fire pond, ash storage area, and the wood fuel storage area contain wastes r |
Violation |
None |
Report |
SPI Burney Division |
436971 |
R5-2020-0017 |
Y |
1147202 |
02/03/2025 |
Unauthorized Discharge |
The fire pond, ash storage area, and the wood fuel storage area contain wastes r |
Violation |
None |
Report |
SPI Burney Division |
436971 |
R5-2020-0017 |
Y |
1147201 |
02/03/2025 |
Unauthorized Discharge |
The fire pond, ash storage area, and the wood fuel storage area contain wastes r |
Violation |
None |
Report |
SPI Burney Division |
436971 |
R5-2020-0017 |
Y |
1147200 |
02/03/2025 |
Unauthorized Discharge |
The fire pond, ash storage area, and the wood fuel storage area contain wastes r |
Violation |
None |
Report |
SPI Burney Division |
436971 |
R5-2020-0017 |
Y |
1140716 |
01/15/2025 |
OEV |
pH Instantaneous Minimum limit is 6 SU and reported value was 5.62 SU at EFF-002 |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1139658 |
12/30/2024 |
Deficient Monitoring |
SPI did not measure settled matter depth for LND-005. |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1139659 |
12/29/2024 |
Deficient Monitoring |
SPI did not measure settled matter depth for LND-006. |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1139657 |
12/29/2024 |
Deficient Monitoring |
SPI did not measure settled matter depth for LND-004. |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1139656 |
12/29/2024 |
Deficient Monitoring |
SPI did not measure settled matter depth for LND-003. |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1137888 |
11/21/2024 |
Deficient Monitoring |
Flow readings were not taken on the first day of discharge for RSW-003 and RSW-0 |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1137887 |
11/21/2024 |
Deficient Monitoring |
SPI did not complete an acute toxicity test the first day of discharge. |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
1137886 |
11/21/2024 |
Deficient Monitoring |
SPI did not complete a Total Hardness (as CaCO3) analysis for RSW-03 and RSW-04 |
Violation |
N |
eSMR |
SPI Burney Division |
436971 |
R5-2020-0017 |
N |
Report defaults to display violations within the last year. Click here to see last five years of violations. Refer to the Interactive Violation Report for more data.
|