| Violation ID |
Occurrence Date |
Violation Type |
Violation Description(-) |
Violation Status |
Priority |
Source |
Facility Name |
Violated Reg. Meas. ID |
Violated Reg. Meas. Order No. |
Linked to Enf. |
| S898391 |
08/31/2025 |
SW - Deficient Report |
Phase III Corrective Action Plan Deficient |
Violation |
N |
Internal Report |
BAS Recycling |
S539093 |
R8-2012-0012 |
Y |
| S890691 |
07/30/2023 |
SW - Deficient Report |
Failure to submit adequate Corrective Action Plan Phase II within 30-days of exceedance. |
Violation |
N |
Internal Report |
BAS Recycling |
S539093 |
R8-2012-0012 |
Y |
| S889042 |
04/04/2024 |
SW - Deficient BMP Implementation |
Failure to sweep, implement effective perimeter controls, and perform good housekeeping. The facility had spill stains and failed to stored chemicals in secondary containment. |
Violation |
N |
Inspection |
BAS Recycling |
S539093 |
R8-2012-0012 |
Y |
| S889041 |
04/04/2024 |
SW - Incomplete/Insufficient SWPPP |
The SWPPP's pollutant source assessment does not evaluate metals. The site map is missing a discharge point. The general SWPPP information is out of date. |
Violation |
N |
Inspection |
BAS Recycling |
S539093 |
R8-2012-0012 |
Y |
| S886606 |
03/28/2022 |
SW - Effluent |
zinc NEL exceedance |
Violation |
N |
Report |
Lakin Tire West LLC |
S520410 |
2014-0057-DWQ |
Y |
| S886605 |
07/07/2022 |
SW - Late Report |
Late ad hoc reports submitted 50 days late and 68 days late |
Violation |
N |
Report |
Lakin Tire West LLC |
S520410 |
2014-0057-DWQ |
Y |
| S886604 |
07/15/2021 |
SW - Late Report |
Late ad hoc reports submitted, 145 days late, 92 days late, 84 days late |
Violation |
N |
Report |
Lakin Tire West LLC |
S520410 |
2014-0057-DWQ |
Y |
| S881606 |
03/30/2022 |
SW - Effluent |
Effluent Limit violation for Total Zinc as listed in the Stormwater Industrial General Permit. |
Violation |
N |
Report |
Lakin Tire West LLC |
S520410 |
2014-0057-DWQ |
Y |
| S881605 |
03/30/2022 |
SW - Effluent |
Effluent Limit violation for Total Zinc as listed in the Stormwater Industrial General Permit. |
Violation |
N |
Report |
Lakin Tire West LLC Building 3 |
S520420 |
2014-0057-DWQ |
Y |
|
Report currently showing last five years of violations. Click here to return to viewing one year of violations. Refer to the Interactive Violation Report for more data.
|