General Information
Party ID Party Name Party Classification Mailing Address Work Phone Email/Website
S649427 NFV 1 Investments LLC Privately-Owned Business PO Box 3151 Shell Beach, CA 93448 N/A N/A
  
  
  
  
Expand/Contract Related Places
Related Places
Place ID Place Name County Region Place Type Relationship to Party Relationship Start Date Relationship End Date
S917408 The Preserve at Millerton Lake Madera 5F Facility Discharger 11/06/2023 None
S859170 The Preserve at Millerton Lake Phase 1 Madera 5F Facility Discharger 09/28/2017 None
Total Related Places: 2
  
  
  
  
Expand/Contract Related Parties
Related Parties
Party ID Party Name Party Type Role/Relationship Relationship Start Date Relationship End Date Classification
N/A Richard Loughead Contact Owner Contact N/A N/A N/A
Total Related Parties: 1
  
  
  
  
Expand/Contract Regulatory Measures
Regulatory Measures (non-enforcement)
Reg. Measure ID Regulatory Measure Type Region WDID Status Program Order No. RM Effective Date RM Termination Date Relationship Relationship Start Date Relationship End Date Amended?
S567607 Construction 5F 5F20C402651 Active CONSTW 2009-0009-DWQ 12/04/2023 None Discharger 11/06/2023 None None
Total Regulatory Measures: 1
  
  
  
  
Expand/Contract Violations
Violations within the past five years
Violation ID Occurrence Date Violation Type Violation Description(-) Violation Status Priority Source Facility Name Violated Reg. Meas. ID Violated Reg. Meas. Order No. Linked to Enf.
S903675 09/02/2024 SW - Late Report Discharger failed to submit the 2023-2024 Annual Report by 1 September 2024 per the CGP. Violation N Report The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S903032 09/02/2023 SW - Late Report Discharger failed to submit the 2022-2023 Annual Report by 1 September 2023 per the CGP. Violation N Report The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S894708 09/02/2025 SW - Failure to Obtain Permit Failure to obtain coverage under the 2022 CGP by 09/01/2025. Violation N Internal Report The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S885237 12/21/2022 SW - Deficient BMP Implementation Violation #9 Attachment D, Part E.4. Sediment Controls, which states: Risk Level 2 dischargers shall apply linear sediment controls along the toe of the slope, face of the slope, and at the grade breaks of exposed slopes to comply with sheet flow lengths in accordance with Table 1. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S885236 12/21/2022 SW - Deficient BMP Implementation Violation #10 Attachment D, Part F. Run-on and Run-off Controls, which states: Risk Level 2 dischargers shall effectively manage all run-on, all runoff within the site and all runoff that discharges off the site. Run-on from off site shall be directed away from all disturbed areas or shall collectively be in compliance with the effluent limitations in this General Permit. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S884913 12/21/2022 SW - Deficient BMP Implementation Violation #8 Attachment D, Part E.3 Sediment Controls, which states: Additional Risk Level 2 Requirement: Risk Level 2 dischargers shall implement appropriate erosion control BMPs (runoff control and soil stabilization) in conjunction with sediment control BMPs for areas under active construction. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S884912 12/21/2022 SW - Deficient BMP Implementation Violation #7 boundary line of silt fencing along the base of slope within Cottonwood Creek. Board staff did not identify the proposed BMPs during the site visit. Attachment D, Part E.1 Sediment Controls, which states: Risk Level 2 dischargers shall establish and maintain effective perimeter controls and stabilize all construction entrances and exits to sufficiently control erosion and sediment discharges from the site. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S884911 12/21/2022 SW - Deficient BMP Implementation Violation #6 Attachment D, Part D.2. Erosion Controls, which states: Risk Level 2 dischargers shall provide effective soil cover for inactive areas and all finished slopes, open space, utility backfill, and completed lots. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S884908 12/21/2022 SW - Deficient BMP Implementation Violation #5 Attachment D, Part B.5.e, Good Site Management "Housekeeping", which states: Ensure effectiveness of existing BMPs to reduce or prevent pollutants in storm water discharges and authorized non-storm water discharges. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S884907 12/21/2022 SW - Deficient BMP Implementation Violation #4 Attachment D, Part B.2.i, Good Site Management "Housekeeping", which states: Ensure the containment of concrete washout areas and other washout areas that may contain additional pollutants so there is no discharge into the underlying soil and onto the surrounding areas. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S884906 12/21/2022 SW - Deficient BMP Implementation Violation #3 Attachment D, Part B.1.b, Good Site Management "Housekeeping", which states: Cover and berm loose stockpiled construction materials that are not actively being used (i.e. soil, spoils, aggregate, fly-ash, stucco, hydrated lime, etc.). Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S884903 12/21/2022 SW - Deficient BMP Implementation Violation #2 Section V.A.2, Narrative Effluent Limitations, which states: Dischargers shall minimize or prevent pollutants in storm water discharges and authorized non-storm water discharges through the use of controls, structures, and management practices that achieve BAT for toxic and non-conventional pollutants and BCT for conventional pollutants. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
S884902 12/21/2022 SW - Deficient Report Violation #1 As referenced within the File Review section of the enclosed Inspection Report, the Project?s SWPPP maps do not reflect the Project?s expanded footprint of the observed land disturbance. Section II.C.2, Revising Permit Coverage for Change of Acreage or New Ownership, which states: Within 30 days of a reduction or increase in total disturbed acreage, the discharger shall electronically file revisions to the PRDs that include: a. A revised NOI indicating the new project size; b. A revised site map showing the acreage of the site completed, acreage currently under construction, acreage sold/transferred or added, and acreage currently stabilized in accordance with the Conditions for Termination of Coverage in Section II.D below. c. SWPPP revisions, as appropriate; and d. Certification that any new landowners have been notified of applicable requirements to obtain General Permit coverage. The certification shall include the name, address, telephone number, and e-mail address of the new landowner. e. If the project acreage has increased, dischargers shall mail payment of revised annual fees within 14 days of receiving the revised annual fee notification. Violation N Inspection The Preserve at Millerton Lake Phase 1 S491444 2009-0009-DWQ Y
Report currently showing last five years of violations. Click here to return to viewing one year of violations. Refer to the Interactive Violation Report for more data.
Total Violations: 13
*Click the "(+/-) Violation Description" link to expand and contract the violation description.
  
  
  
  
Expand/Contract Enforcement Actions
Enforcement Actions
Enforcement ID Enforcement Type Enf. Order No. Title Program Effective Date Status
S469304 1st Annual Report Notice of Non-Compliance None 5F20C382022 CONSTW 02/26/2025 Active
S468565 1st Annual Report Notice of Non-Compliance None 5F20C382022 CONSTW 02/25/2025 Active
S459557 Notice of Violation None 5F20C382022 CONSTW 09/05/2025 Active
S450059 Staff Enforcement Letter None 5F20C382022 CONSTW 05/19/2023 Active
S450048 Notice of Violation None 5F20C382022 CONSTW 01/12/2023 Active
Total Enforcement Actions: 5
  
  
  
  
Expand/Contract Enforcement Actions
Regulatory Measures linked to Related Parties
Reg. Measure ID Organization Regulatory Measure Type Program Effective Date Status
Total Regulatory Measures linked to Related Parties: 0
  
  
The current report was generated with data as of: 05/20/2026
Regional Boards are in the process of entering backlogged data.
As a result, data may be incomplete.
Back to Main Page  |  Back to Top of Page