| S903433 |
09/02/2024 |
SW - Late Report |
Discharger failed to submit the 2023-2024 Annual Report by 1 September 2024 per |
Violation |
N |
Report |
Aquatic Center and Larry Itliong Unity Park Project |
S557293 |
2009-0009-DWQ |
Y |
| S903431 |
09/02/2024 |
SW - Late Report |
Discharger failed to submit the 2023-2024 Annual Report by 1 September 2024 per |
Violation |
N |
Report |
2022 Albany Stradley Stump Improvement |
S556168 |
2009-0009-DWQ |
Y |
| S903211 |
09/02/2023 |
SW - Late Report |
Discharger failed to submit the 2022-2023 Annual Report by 1 September 2023 per |
Violation |
N |
Report |
Aquatic Center and Larry Itliong Unity Park Project |
S557293 |
2009-0009-DWQ |
Y |
| S903208 |
09/02/2023 |
SW - Late Report |
Discharger failed to submit the 2022-2023 Annual Report by 1 September 2023 per |
Violation |
N |
Report |
2022 Albany Stradley Stump Improvement |
S556168 |
2009-0009-DWQ |
Y |
| S902184 |
10/16/2025 |
SW - Late Report |
Failure to submit the 2024-2025 Annual Report |
Violation |
N |
Report |
Phase II Small MS4 |
S440621 |
2013-0001-DWQ |
Y |
| S890623 |
10/16/2024 |
SW - Late Report |
Failure to submit 2023-2024 Annual Report by 15 October 2024. |
Violation |
N |
Report |
Phase II Small MS4 |
S440621 |
2013-0001-DWQ |
Y |
| S885020 |
10/16/2022 |
SW - Late Report |
Late 2021-2022 Annual Report. Not submitted on time. |
Violation |
N |
Inspection |
Phase II Small MS4 |
S440621 |
2013-0001-DWQ |
Y |
|