Violation ID |
Occurred Date |
Violation Type |
(-) Violation Description |
Corrective Action |
Status |
Classification |
Source |
1134069 |
01/13/2024 |
SSOS |
Type: Category 1 Spill; Debris from Construction caused 1370 gallons of sewage to spill from Manhole at Intersection of Anna St and Holm Rd to Drainage Conveyance System, Drainage Conveyance System that discharges to surface water, Street/Curb and Gutter (2 3), Surface Water |
Other (specify below). Debris in sewer main including broken manhole lid, manhole hook and coldmix was dropped and left in the line from outside contractor |
Violation |
A |
SSO |
1134068 |
11/14/2023 |
SSOS |
Type: Category 1 Spill; Pump Station Failure - Controls, Pump Station Failure - Mechanical, Pump Station Failure - Power caused 120 gallons of sewage to spill from Lateral Clean Out (Private), Manhole at Montebello Dr to Drainage Conveyance System, Paved Surface, Street/Curb and Gutter (2 3) |
Repaired Facilities or Replaced Defect. PGE Power flicker caused HMI issues
We had instrumental techs add additional alarms for earlier and multiple warnings |
Violation |
A |
SSO |
1086450 |
02/18/2021 |
SSOS |
Type: Category 1. Pump Station Failure-Controls;Bubbler pump failure caused 2299.0 gallons of sewage to spill from Pump station at Pump Station 15 Main St to Drainage Channel;Unpaved surface. Surface water body affected (Struve Slough). |
Cleaned-Up;Mitigated Effects of Spill;Contained all or portion of spill;Returned All Spill to Sanitary Sewer System. ;Operator started the pumps in hand to pump down the wet well. A Vactor vacuum truck was called in to assist in cleanup. Storm inlet was vacuumed and cleaned. Storm outlet was vacuumed and cleaned. Area at the discharge point was cleaned. |
Violation |
B |
SSO |
Report displays most recent five years of violations. Refer to the Interactive Violation Report for more data.
|