| Violation ID |
Occurred Date |
Violation Type |
(-) Violation Description |
Corrective Action |
Status |
Classification |
Source |
| S894077 |
09/02/2025 |
FOP |
Failure to obtain coverage under the 2022 CGP by 09/01/2025. |
|
Violation |
B |
Internal Report |
| S888391 |
11/30/2023 |
MS4 Order Condition |
Failure to implement linear sediment controls. Continuation of these conditions was further alleged in the NOV dated 4/30/25. |
|
Violation |
B |
Inspection |
| S888389 |
11/30/2023 |
MS4 Order Condition |
failure implement controls, structures, and management practices that achieve BAT and BCT for conventional, non-conventional and toxic pollutants. Continuation of these conditions was further alleged in the NOV dated 4/30/25. |
|
Violation |
S |
Inspection |
| S888392 |
11/30/2023 |
MS4 Order Condition |
Failure to implement good site management (“housekeeping”) measures. (Supplemental entry: These conditions were also observed during Water Board staff's 4/24/24 inspection and in the Discharger's 5/29/24 and 7/3/24 photos submitted with its weekly reports. These later allegations are included in the NOV dated 4/30/25.) |
|
Violation |
B |
Inspection |
| S888394 |
11/30/2023 |
MS4 Order Condition |
Failure to implement effective soil cover for inactive areas and all finished slopes. Continuation of these conditions was further alleged in the NOV dated 4/30/25, |
|
Violation |
B |
Inspection |
| S888390 |
11/30/2023 |
Deficient BMP Implementation |
Failure to implement appropriate erosion control BMPs |
|
Violation |
B |
Inspection |
| S889175 |
02/08/2023 |
FOP |
5 acres of ground disturbance for access road to municipal supply water tanks and access road to project from Orcutt Hill Rd / open space trailhead. First reported by SB County grading inspector February 8, 2023, requesting LRP to install ESC BMPs. |
|
Violation |
B |
Inspection |
| S888393 |
09/02/2022 |
LREP |
Failure to electronically certify and submit annual reports. 2021-2022 and 2022-2023 Annual Reports (AR) submitted 02/01/2024. 2021-2022 incorrectly entered "Construction was not active and had not begun for three months or longer within this annual reporting period." Clear and grub work started Sept 2021, mass grading began mid Nov 2021. Work through winter, no samples collected, job stop work orders by SB County for lack of SW compliance. 2022-2023 equally inaccurate. Continuation on these circumstances was further alleged in the NOV dated 4/30/25. |
|
Violation |
B |
Report |
|
Report displays most recent five years of violations. Refer to the Interactive Violation Report for more data.
|