Violation ID |
Occurred Date |
Violation Type |
(-) Violation Description |
Corrective Action |
Status |
Classification |
Source |
1123273 |
01/02/2024 |
LREP |
Once Only OneTime ( TECHRPT ) (Bioaccumulation Study) report for 2020/01/01 (2273547) was due on 01-JAN-24 |
|
Violation |
B |
Report |
1123272 |
01/02/2024 |
LREP |
Once Only OneTime ( TECHRPT ) (Rocky Intertidal Marine Life Survey) report for 2020/01/01 (2273546) was due on 01-JAN-24 |
|
Violation |
B |
Report |
1123257 |
11/21/2023 |
Surface Water |
instantaneous max TSS readings of RSW-001B exceeded max of 60mg/L, and found significant effect from T-test (p=.003). It is believed that this was due to recent construction work done associated with the TRINIDAD HARBOR ASBS STORMWATER RUNOFF MANAGEMENT AND GREEN INFRASTRUCTURE ENHANCEMENT PROJECT. This was the first backwash done after new riprap and boulders were placed seaward of our discharge pipe. Newly deposited sediment being flushed out was the probable cause of the high values. |
Samples were taken (and results received) after backwash discharge had stopped. No corrective action was possible. |
Violation |
B |
eSMR |
1121849 |
11/02/2023 |
LREP |
Quarterly SMR ( MONNPDES ) report for Q3 2023 (2273582) was due on 01-NOV-23 |
|
Violation |
B |
Report |
1120092 |
09/02/2023 |
LREP |
Semi-Annual SMR ( MONNPDES ) report for H1 2023 (2273605) was due on 01-SEP-23 |
|
Violation |
B |
Report |
1102127 |
03/02/2022 |
LREP |
Annual SMR ( MONNPDES ) report for 2021 (2273537) was due on 01-MAR-22 |
|
Violation |
B |
Report |
1096523 |
11/02/2021 |
LREP |
Quarterly SMR ( MONNPDES ) report for Q3 2021 (2273574) was due on 01-NOV-21 |
|
Violation |
B |
Report |
1097880 |
09/10/2021 |
LREP |
Semiannual SMR ( MONNPDES ) report for H1 2021 (2273601) was due on September 1, 2021. |
|
Violation |
B |
Report |
1097884 |
11/05/2020 |
LREP |
Quarterly SMR ( MONNPDES ) report for Q3 2020 (2273570) was due on November 1, 2020. |
|
Violation |
B |
Report |
1097868 |
10/02/2020 |
LREP |
Semiannual SMR ( MONNPDES ) report for H1 2020 (2273599) was due on September 1, 2020. |
|
Violation |
B |
Report |
1097882 |
08/25/2020 |
LREP |
Quarterly SMR ( MONNPDES ) report for Q2 2020 (2273569) was due on August 1, 2020. |
|
Violation |
B |
Report |
1097893 |
03/30/2020 |
LREP |
Semiannual SMR ( MONRPT ) report (2225152) was due on March 2, 2020. |
|
Violation |
B |
Report |
1097891 |
03/04/2020 |
LREP |
2019 Annual Report ( SUMRPT ) report (2155712) was due on March 2, 2020. |
|
Violation |
B |
Report |
1097894 |
02/04/2020 |
LREP |
Quarterly SMR ( MONRPT ) report (2225151) was due on February 3, 2020. |
|
Violation |
B |
Report |
1097902 |
01/02/2020 |
LREP |
Monthly SMR ( MONRPT ) report (2249966) was due on January 1, 2020. |
|
Violation |
B |
Report |
1097901 |
12/16/2019 |
LREP |
Monthly SMR ( MONRPT ) report (2238970) was due on December 1, 2019. |
|
Violation |
B |
Report |
Report displays most recent five years of violations. Refer to the Interactive Violation Report for more data.
|