Violation ID |
Occurred Date |
Violation Type |
(-) Violation Description |
Corrective Action |
Status |
Classification |
Source |
1096830 |
07/15/2021 |
Deficient Reporting |
(2Q 2021) Failure to provide lab reports for constituents tested for groundwater monitoring. Missing lab reports for Monitoring Well 4 through Monitoring Well 8. |
|
Violation |
B |
Report |
1096766 |
06/30/2021 |
Deficient Reporting |
(2 Q 2021) Failure to monitor phosphorous semi annually in effluent as required by MRP. |
|
Violation |
B |
Report |
1096768 |
06/30/2021 |
Deficient Reporting |
(2Q2021) Failure to monitor water supply Total Dissolved Solids, Sulfate, Chloride, Boron, Nitrate-N, Fecal Coliform, Total Coliform, Enteroccocus
as required by MRP. |
|
Violation |
B |
Report |
1096763 |
06/07/2021 |
Deficient Reporting |
(2Q 2021); Failure to monitor monthly (June) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1097499 |
06/04/2021 |
Deficient Reporting |
(2Q2019); Failure to monitor monthly (June) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096762 |
05/05/2021 |
Deficient Reporting |
(2Q 2021); Failure to monitor monthly (May) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096852 |
04/15/2021 |
Deficient Reporting |
(1Q2021) Failure to monitor water supply Total Dissolved Solids, Sulfate, Chloride, Boron, Nitrate-N, Fecal Coliform, Total Coliform, Enteroccocus
as required by MRP. |
|
Violation |
B |
Report |
1096832 |
04/15/2021 |
LREP |
1Q 2021: The report was due on 4/15/2021 and the report was received on 4/28/2021. The report was 13 days late. |
|
Violation |
B |
Report |
1096760 |
04/07/2021 |
Deficient Reporting |
(2Q 2021); Failure to monitor monthly (April) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096842 |
03/02/2021 |
Deficient Reporting |
(1Q 2021); Failure to monitor monthly (March) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096838 |
02/03/2021 |
Deficient Reporting |
(1Q 2021); Failure to monitor monthly (February) temperature as required by MRP. |
|
Violation |
B |
Report |
1096850 |
01/15/2021 |
Deficient Reporting |
(4Q2020) Failure to monitor water supply Total Dissolved Solids, Sulfate, Chloride, Boron, Nitrate-N, Fecal Coliform, Total Coliform, Enteroccocus
as required by MRP. |
|
Violation |
B |
Report |
1096846 |
01/15/2021 |
LREP |
4Q2020 Late Report (1/22/2021). Monitoring Report received 7 days late from due date of 1/15/2021. |
|
Violation |
B |
Report |
1096837 |
01/07/2021 |
Deficient Reporting |
(1Q 2021); Failure to monitor monthly ( January) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096845 |
12/31/2020 |
Deficient Reporting |
(4 Q 2020) Failure to monitor phosphorous semi annually in effluent as required by MRP. |
|
Violation |
B |
Report |
1096851 |
12/31/2020 |
Deficient Reporting |
(4Q 2020) Failure to provide lab reports for constituents tested for groundwater monitoring. Missing lab reports for Monitoring Well 4 and Monitoring Well 5. |
|
Violation |
B |
Report |
1096849 |
12/31/2020 |
Deficient Reporting |
(4Q 2020); Failure to monitor monthly (December) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096848 |
11/30/2020 |
Deficient Reporting |
(4Q 2020); Failure to monitor monthly (November) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096847 |
10/31/2020 |
Deficient Reporting |
(4Q 2020); Failure to monitor monthly (October) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096853 |
10/15/2020 |
LREP |
3Q2020 Late Report (10/24/2020): Monitoring Report received 9 days late from due date of 10/15/2020. |
|
Violation |
B |
Report |
1096857 |
09/30/2020 |
Deficient Reporting |
(3Q2020) Failure to monitor water supply Total Dissolved Solids, Sulfate, Chloride, Boron, Nitrate-N, Fecal Coliform, Total Coliform, Enteroccocus
as required by MRP. |
|
Violation |
B |
Report |
1096856 |
09/14/2020 |
Deficient Reporting |
(3Q 2020); Failure to monitor monthly (September) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096855 |
08/05/2020 |
Deficient Reporting |
(3Q 2020); Failure to monitor monthly (August) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096854 |
07/15/2020 |
Deficient Reporting |
(3Q 2020); Failure to monitor monthly (July) temperature in effluent as required by MRP. |
|
Violation |
B |
Report |
1096858 |
07/15/2020 |
Deficient Reporting |
2Q2020 Late Report (07/24/2020): Monitoring Report received 9 days late from due date of 07/15/2020. |
|
Violation |
B |
Report |
Report displays most recent five years of violations. Refer to the Interactive Violation Report for more data.
|