Violation ID |
Occurred Date |
Violation Type |
(-) Violation Description |
Corrective Action |
Status |
Classification |
Source |
1138487 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-1 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138534 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138491 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-2 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138495 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-3 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138500 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138510 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138515 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138521 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138527 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Boron in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138533 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Chloride in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138499 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Chloride in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138504 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Chloride in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138509 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Chloride in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138514 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Chloride in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138520 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Chloride in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138526 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Chloride in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138492 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Color in MW-2 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138522 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Color in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138529 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Color in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138505 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Odor in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138486 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-1 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138532 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138490 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-2 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138494 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-3 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138498 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138503 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138508 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138513 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138519 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138525 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Sulfate in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138516 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Surfactants in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138488 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Coliform in MW-1 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138496 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Coliform in MW-3 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138501 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Coliform in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138506 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Coliform in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138511 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Coliform in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138517 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Coliform in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138523 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Coliform in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138530 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Coliform in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138485 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-1 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138531 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138489 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-2 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138493 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-3 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138497 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138502 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138507 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138512 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138518 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138524 |
07/31/2024 |
DMON |
3Q2024; Failure to monitor Total Dissolved Solids in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137505 |
06/30/2024 |
DMON |
2Q2023; Failure to monitor Boron in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138356 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-1 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138438 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138452 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138371 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-3 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138381 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138389 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138401 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138456 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138417 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138427 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138436 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138379 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138454 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138399 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138455 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138415 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138458 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138453 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Color in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138419 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Color in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138459 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Color in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138470 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138482 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138471 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138472 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138473 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138474 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138475 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138479 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138480 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138481 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138448 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138391 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Odor in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138354 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-1 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138434 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138362 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138368 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-3 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138377 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138387 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138397 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138407 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138413 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138425 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138457 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Surfactants in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138358 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-1 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138440 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138364 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138373 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-3 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138383 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138393 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138403 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138409 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138421 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138429 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138352 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-1 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138431 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138432 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138360 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138366 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-3 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138375 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138385 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138395 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138405 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138411 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138423 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138460 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138469 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138461 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138462 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138463 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138464 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138465 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138466 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138467 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138468 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138447 |
06/30/2024 |
DMON |
2Q2024; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138451 |
06/30/2024 |
Deficient Reporting |
2Q2024; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of June 2024. |
|
Violation |
B |
Report |
1138450 |
05/31/2024 |
Deficient Reporting |
2Q2024; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of May 2024. |
|
Violation |
B |
Report |
1138355 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138437 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138369 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-3 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138380 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138388 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138400 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138416 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138426 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Boron in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138435 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138378 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138398 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138414 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Chloride in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138418 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Color in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138390 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Odor in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138353 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138433 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138361 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138367 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-3 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138376 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138386 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138396 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138406 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138412 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138424 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Sulfate in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138357 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138439 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138363 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138372 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-3 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138382 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138392 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138402 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138408 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138420 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138428 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Coliform in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138351 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138430 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138359 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138365 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-3 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138374 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138384 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138394 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138404 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138410 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138422 |
04/30/2024 |
DMON |
2Q2024; Failure to monitor Total Dissolved Solids in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138449 |
04/30/2024 |
Deficient Reporting |
2Q2024; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of April 2024. |
|
Violation |
B |
Report |
1138341 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138350 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138342 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138343 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138344 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138345 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138346 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138347 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138348 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138349 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138327 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138331 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138340 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138332 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138333 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138334 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138335 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138336 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138337 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138338 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138339 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138326 |
03/31/2024 |
DMON |
1Q2024; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138330 |
03/31/2024 |
Deficient Reporting |
1Q2024; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of March 2024. |
|
Violation |
B |
Report |
1138175 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138099 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138115 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138123 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138135 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138145 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138155 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138165 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138173 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138097 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138113 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138121 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138133 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138143 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138153 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138157 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Color in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138125 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Odor in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138089 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138171 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138095 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138105 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138111 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138119 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138131 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138141 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138151 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138163 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138177 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Surfactants in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138091 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138101 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138107 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138127 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138137 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138147 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138159 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138167 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138087 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138169 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138093 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138103 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138109 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138117 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138129 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138139 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138149 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138161 |
02/29/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138329 |
02/29/2024 |
Deficient Reporting |
1Q2024; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of February 2024. |
|
Violation |
B |
Report |
1138166 |
01/31/2024 |
BMP |
1Q2024; Failure to monitor Total Coliform in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138174 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138098 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138114 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138122 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138134 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138144 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138154 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138164 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Boron in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138172 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138096 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138112 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138120 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138132 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138142 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138152 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Chloride in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138156 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Color in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138124 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Odor in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138088 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138170 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138094 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138104 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138110 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138118 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138130 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138140 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138150 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138162 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Sulfate in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138176 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Surfactants in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138090 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138100 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138106 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138126 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138136 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138146 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138158 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Coliform in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138086 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138168 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138092 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138102 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138108 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138116 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138128 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138138 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138148 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138160 |
01/31/2024 |
DMON |
1Q2024; Failure to monitor Total Dissolved Solids in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138328 |
01/31/2024 |
Deficient Reporting |
1Q2024; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of January 2024. |
|
Violation |
B |
Report |
1138044 |
01/31/2024 |
Deficient Reporting |
Failure to report the following for the office OWTS: name and address of the party responsible for operation and maintenance, frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1138042 |
01/31/2024 |
Deficient Reporting |
Failure to report the following for the production plant OWTS: name and address of the party responsible for operation and maintenance, frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1138043 |
01/31/2024 |
Deficient Reporting |
Failure to report the following for the warehouse OWTS: name and address of the party responsible for operation and maintenance, frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1138064 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138073 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138065 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138066 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138067 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138068 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138069 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138070 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138071 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138072 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138053 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138054 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138063 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138055 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138056 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138057 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138058 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138059 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138060 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138061 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138062 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138052 |
12/31/2023 |
DMON |
4Q2023; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1138076 |
12/31/2023 |
Deficient Reporting |
4Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of December 2023. |
|
Violation |
B |
Report |
1138075 |
11/30/2023 |
Deficient Reporting |
4Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of November 2023. |
|
Violation |
B |
Report |
1138078 |
11/30/2023 |
Deficient Reporting |
4Q2023; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of November 2023. |
|
Violation |
B |
Report |
1138049 |
11/16/2023 |
OEV |
Fecal Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 1600 MPN/100 mL. |
|
Violation |
B |
Report |
1138051 |
11/16/2023 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 2419.6 MPN/100 mL. |
|
Violation |
B |
Report |
1138047 |
11/16/2023 |
CAT1 |
Chloride Daily Maximum limit is 110 mg/L and reported value was 120 mg/L. |
|
Violation |
B |
Report |
1138045 |
11/16/2023 |
CAT1 |
Fixed Dissolved Solids (FDS) Daily Maximum limit is 1500 mg/L and reported value was 1670 mg/L. |
|
Violation |
B |
Report |
1138046 |
11/09/2023 |
CAT1 |
Nitrite, Total (as N) Daily Maximum limit is 1 mg/L and reported value was 2.2 mg/L. |
|
Violation |
B |
Report |
1138082 |
11/06/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform of effluent during the week of 11/6/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1138085 |
11/06/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform of effluent during the week of 11/6/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1138038 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Boron in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137999 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Boron in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138008 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Boron in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138013 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Boron in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138018 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Boron in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138023 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Boron in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138028 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Boron in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138032 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Boron in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138037 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Chloride in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137998 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Chloride in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138012 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Chloride in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138022 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Chloride in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138000 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Color in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138029 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Color in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138019 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Nitrate as Nitrogen in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137994 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Nitrite as Nitrogen in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138004 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Odor in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138014 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Odor in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138024 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Odor in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137993 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138036 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137997 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138003 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138007 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138011 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138017 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138021 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138027 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138031 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Sulfate in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137995 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138001 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138005 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138009 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138015 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138025 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138033 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137992 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138034 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137996 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138002 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138006 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138010 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138016 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138020 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138026 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138030 |
10/31/2023 |
DMON |
4Q2023; Failure to monitor Total Dissolved Solids in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1138074 |
10/31/2023 |
Deficient Reporting |
4Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of October 2023. |
|
Violation |
B |
Report |
1138077 |
10/31/2023 |
Deficient Reporting |
4Q2023; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of October 2023. |
|
Violation |
B |
Report |
1138081 |
10/30/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform of effluent during the week of 10/30/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1138084 |
10/30/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform of effluent during the week of 10/30/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1138080 |
10/23/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform of effluent during the week of 10/23/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1138083 |
10/23/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform of effluent during the week of 10/23/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1138048 |
10/19/2023 |
OEV |
Fecal Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 1600 MPN/100 mL. |
|
Violation |
B |
Report |
1138050 |
10/19/2023 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 2419.6 MPN/100 mL. |
|
Violation |
B |
Report |
1137650 |
10/09/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform of effluent during the week of 10/9/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137652 |
10/09/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform of effluent during the week of 10/9/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137649 |
10/02/2023 |
DMON |
4Q2023; Failure to monitor Fecal Coliform of effluent during the week of 10/2/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137651 |
10/02/2023 |
DMON |
4Q2023; Failure to monitor Total Coliform of effluent during the week of 10/2/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137991 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137953 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137962 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137967 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137972 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137977 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137982 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137986 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137990 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137952 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137966 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137976 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137954 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Color in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137983 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Color in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137935 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137945 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137936 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137937 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137938 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137939 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137940 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137941 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137942 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137944 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137642 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137948 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Nitrite as Nitrogen in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137973 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Nitrite as Nitrogen in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137958 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Odor in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137968 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Odor in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137978 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Odor in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137947 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137989 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137951 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137957 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137961 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137965 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137971 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137975 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137981 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137985 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137949 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137955 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137959 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137963 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137969 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137979 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137987 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137946 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137988 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137950 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137956 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137960 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137964 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137970 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137974 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137980 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137984 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137925 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137934 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137926 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137927 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137928 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137929 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137930 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137931 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137932 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137933 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137641 |
09/30/2023 |
DMON |
3Q2023; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137645 |
09/30/2023 |
Deficient Reporting |
3Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of September 2023. |
|
Violation |
B |
Report |
1137648 |
09/30/2023 |
Deficient Reporting |
3Q2023; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of September 2023. |
|
Violation |
B |
Report |
1137906 |
09/25/2023 |
DMON |
3Q2023; Failure to monitor Chloride of effluent during the week of 9/25/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137917 |
09/25/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform of effluent during the week of 9/25/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137924 |
09/25/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform of effluent during the week of 9/25/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137905 |
09/18/2023 |
DMON |
3Q2023; Failure to monitor Chloride of effluent during the week of 9/18/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137916 |
09/18/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform of effluent during the week of 9/18/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137923 |
09/18/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform of effluent during the week of 9/18/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137666 |
09/14/2023 |
OEV |
Fecal Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 1600 MPN/100 mL. |
|
Violation |
B |
Report |
1137669 |
09/14/2023 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 2419.6 MPN/100 mL. |
|
Violation |
B |
Report |
1137904 |
09/04/2023 |
DMON |
3Q2023; Failure to monitor Chloride of effluent during the week of 9/4/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137915 |
09/04/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform of effluent during the week of 9/4/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137922 |
09/04/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform of effluent during the week of 9/4/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137635 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-10 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137602 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-4 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137607 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-5 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137613 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-6 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137619 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-7 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137625 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-8 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137630 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Boron in MW-9 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137634 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-10 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137595 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-2 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137606 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-5 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137618 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-7 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137624 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Chloride in MW-8 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137608 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Color in MW-5 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137626 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Color in MW-8 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137614 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Nitrate as Nitrogen in MW-6 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137609 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Odor in MW-5 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137620 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Odor in MW-7 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137591 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-1 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137633 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-10 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137594 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-2 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137598 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-3 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137601 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-4 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137605 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-5 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137612 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-6 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137617 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-7 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137623 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-8 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137628 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-9 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137629 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Sulfate in MW-9 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137592 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-1 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137596 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-2 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137599 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-3 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137603 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-4 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137610 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-5 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137615 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-6 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137621 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-7 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137631 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform in MW-9 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137590 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-1 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137632 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-10 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137593 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-2 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137597 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-3 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137600 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-4 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137604 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-5 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137611 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-6 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137616 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-7 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137622 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-8 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137627 |
08/31/2023 |
DMON |
3Q2023; Failure to monitor Total Dissolved Solids in MW-9 during the month of August as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137644 |
08/31/2023 |
Deficient Reporting |
3Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of August 2023. |
|
Violation |
B |
Report |
1137647 |
08/31/2023 |
Deficient Reporting |
3Q2023; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of August 2023. |
|
Violation |
B |
Report |
1137665 |
08/31/2023 |
OEV |
Fecal Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 1600 MPN/100 mL. |
|
Violation |
B |
Report |
1137668 |
08/31/2023 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 2419.6 MPN/100 mL. |
|
Violation |
B |
Report |
1137662 |
08/31/2023 |
CAT1 |
Chloride Daily Maximum limit is 110 mg/L and reported value was 130 mg/L. |
|
Violation |
B |
Report |
1137659 |
08/31/2023 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 24 mg/L. |
|
Violation |
B |
Report |
1137658 |
08/24/2023 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 86 mg/L. |
|
Violation |
B |
Report |
1137661 |
08/24/2023 |
CAT1 |
Nitrite, Total (as N) Daily Maximum limit is 1 mg/L and reported value was 2.2 mg/L. |
|
Violation |
B |
Report |
1137910 |
08/21/2023 |
DMON |
3Q2023; Failure to monitor Boron of effluent during the week of 8/21/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137914 |
08/21/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform of effluent during the week of 8/21/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137903 |
08/21/2023 |
DMON |
3Q2023; Failure to monitor Fixed Dissolved Solids of effluent during the week of 8/21/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137921 |
08/21/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform of effluent during the week of 8/21/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137657 |
08/17/2023 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 79 mg/L. |
|
Violation |
B |
Report |
1137660 |
08/17/2023 |
CAT1 |
Nitrite, Total (as N) Daily Maximum limit is 1 mg/L and reported value was 2 mg/L. |
|
Violation |
B |
Report |
1137909 |
08/14/2023 |
DMON |
3Q2023; Failure to monitor Boron of effluent during the week of 8/14/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137913 |
08/14/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform of effluent during the week of 8/14/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137902 |
08/14/2023 |
DMON |
3Q2023; Failure to monitor Fixed Dissolved Solids of effluent during the week of 8/14/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137920 |
08/14/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform of effluent during the week of 8/14/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137656 |
08/10/2023 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 86 mg/L. |
|
Violation |
B |
Report |
1137908 |
08/07/2023 |
DMON |
3Q2023; Failure to monitor Boron of effluent during the week of 8/7/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137912 |
08/07/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform of effluent during the week of 8/7/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137901 |
08/07/2023 |
DMON |
3Q2023; Failure to monitor Fixed Dissolved Solids of effluent during the week of 8/7/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137919 |
08/07/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform of effluent during the week of 8/7/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137907 |
07/31/2023 |
DMON |
3Q2023; Failure to monitor Boron of effluent during the week of 7/31/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137911 |
07/31/2023 |
DMON |
3Q2023; Failure to monitor Fecal Coliform of effluent during the week of 7/31/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137900 |
07/31/2023 |
DMON |
3Q2023; Failure to monitor Fixed Dissolved Solids of effluent during the week of 7/31/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137918 |
07/31/2023 |
DMON |
3Q2023; Failure to monitor Total Coliform of effluent during the week of 7/31/2023 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137643 |
07/31/2023 |
Deficient Reporting |
3Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of July 2023. |
|
Violation |
B |
Report |
1137646 |
07/31/2023 |
Deficient Reporting |
3Q2023; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of July 2023. |
|
Violation |
B |
Report |
1137555 |
07/30/2023 |
LREP |
2Q2023 Late Report (7/31/2023): Monitoring Report received 1 day late from due date of 7/30/2023. |
|
Violation |
B |
Report |
1137664 |
07/27/2023 |
OEV |
Fecal Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 1600.0 MPN/100 mL. |
|
Violation |
B |
Report |
1137667 |
07/27/2023 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 1600 MPN/100 mL. |
|
Violation |
B |
Report |
1137663 |
07/27/2023 |
CAT1 |
Boron, Total Daily Maximum limit is 1 mg/L and reported value was 1.13 mg/L. |
|
Violation |
B |
Report |
1137654 |
07/27/2023 |
CAT1 |
Fixed Dissolved Solids (FDS) Daily Maximum limit is 1500 mg/L and reported value was 1590 mg/L. |
|
Violation |
B |
Report |
1137655 |
07/27/2023 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 79 mg/L. |
|
Violation |
B |
Report |
1137552 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137497 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137588 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137521 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137534 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137542 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137550 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137583 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137503 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137519 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137532 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137483 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Color in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137585 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Color in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137536 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Color in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137571 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137580 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137572 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137573 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137574 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137575 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137576 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137577 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137578 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137579 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137560 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137511 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Nitrate as Nitrogen in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137507 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Odor in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137525 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Odor in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137526 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Odor in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137582 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-1 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137548 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137481 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137487 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-3 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137493 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137501 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137509 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137518 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137530 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137540 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137523 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Surfactants in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137471 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-1 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137554 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137485 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137489 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-3 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137496 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137586 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137513 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137589 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137544 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137581 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-1 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137546 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-10 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137473 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-2 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137584 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-3 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137491 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-4 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137499 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-5 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137587 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-6 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137515 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-7 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137528 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-8 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137538 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-9 during the month of June as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137561 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137570 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137562 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137563 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137564 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137565 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137566 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137567 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137568 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137569 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137559 |
06/30/2023 |
DMON |
2Q2023; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137558 |
06/30/2023 |
Deficient Reporting |
2Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of June 2023. |
|
Violation |
B |
Report |
1137557 |
05/31/2023 |
Deficient Reporting |
2Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of May 2023. |
|
Violation |
B |
Report |
1137551 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137494 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137504 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137520 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137533 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137541 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Boron in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137549 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137502 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137517 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137531 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Chloride in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137482 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Color in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137535 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Color in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137510 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Nitrate as Nitrogen in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137506 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Odor in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137524 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Odor in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137547 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137474 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137486 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-3 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137492 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137500 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137508 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137516 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137529 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137539 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Sulfate in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137522 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Surfactants in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137470 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137553 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137484 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137488 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-3 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137495 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137512 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137543 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Coliform in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137545 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137472 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137490 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137498 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137514 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137527 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137537 |
04/30/2023 |
DMON |
2Q2023; Failure to monitor Total Dissolved Solids in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137556 |
04/30/2023 |
Deficient Reporting |
2Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of April 2023. |
|
Violation |
B |
Report |
1137460 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137469 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137461 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137462 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137463 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137464 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137465 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137466 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137467 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137468 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137449 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137450 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137459 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137451 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137452 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137453 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137454 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137455 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137456 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137457 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137458 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137448 |
03/31/2023 |
DMON |
1Q2023; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137447 |
03/31/2023 |
Deficient Reporting |
1Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of March 2023. |
|
Violation |
B |
Report |
1137273 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137362 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137284 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137301 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137311 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137324 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137334 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137346 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137354 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137271 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137360 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137287 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137309 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137322 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137332 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137344 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137364 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Color in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137336 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Color in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137348 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Color in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137275 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Odor in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137313 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Odor in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137338 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Odor in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137269 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137358 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137281 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137293 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137299 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137307 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137320 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137330 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137342 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137352 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137277 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137366 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137288 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137295 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137303 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137316 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137326 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137267 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137356 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137279 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137291 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137297 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137305 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137318 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137328 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137340 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137350 |
02/28/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137446 |
02/28/2023 |
Deficient Reporting |
1Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of February 2023. |
|
Violation |
B |
Report |
1137337 |
01/31/2023 |
BMP |
1Q2023; Failure to monitor Odor in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137272 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137361 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137283 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137300 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137310 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137323 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137333 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137345 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137353 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Boron in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137270 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137359 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137282 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137308 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137321 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137331 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137343 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Chloride in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137363 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Color in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137335 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Color in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137347 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Color in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137274 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Odor in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137312 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Odor in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137268 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137357 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137280 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137292 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137298 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137306 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137319 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137329 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137341 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137351 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Sulfate in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137276 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137365 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137286 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137294 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137302 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137315 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137325 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Coliform in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137266 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137355 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137278 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137290 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137296 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137304 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137317 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137327 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137339 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137349 |
01/31/2023 |
DMON |
1Q2023; Failure to monitor Total Dissolved Solids in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137445 |
01/31/2023 |
Deficient Reporting |
1Q2023; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of January 2023. |
|
Violation |
B |
Report |
1137444 |
01/31/2023 |
Deficient Reporting |
Failure to report the following for the office OWTS: name and address of the party responsible for operation and maintenance, frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1137442 |
01/31/2023 |
Deficient Reporting |
Failure to report the following for the production plant OWTS: name and address of the party responsible for operation and maintenance, frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1137443 |
01/31/2023 |
Deficient Reporting |
Failure to report the following for the warehouse OWTS: name and address of the party responsible for operation and maintenance, frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1137198 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-1 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137258 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-10 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137206 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-2 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137216 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-4 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137223 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-5 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137231 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-6 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137238 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-7 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137246 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-8 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137252 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-9 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137197 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-1 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137257 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-10 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137205 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-2 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137222 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-5 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137230 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-6 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137237 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-7 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137245 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-8 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137259 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Color in MW-10 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137239 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Color in MW-7 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137247 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Color in MW-8 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137201 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137262 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137208 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137212 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137218 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137227 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137233 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137241 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137248 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137254 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137265 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137200 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Odor in MW-1 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137225 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Odor in MW-5 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137240 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Odor in MW-7 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137196 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-1 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137256 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-10 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137204 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-2 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137210 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-3 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137215 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-4 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137221 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-5 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137229 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-6 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137236 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-7 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137244 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-8 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137251 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-9 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137202 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-1 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137260 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-10 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137209 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-2 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137213 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-3 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137219 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-4 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137226 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-5 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137234 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-6 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137195 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137255 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137203 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-3 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137214 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-4 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137220 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137228 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137235 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137243 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137250 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of December as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137199 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137261 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137207 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137211 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137217 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137224 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137232 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137242 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137249 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137253 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137264 |
12/31/2022 |
DMON |
4Q2022; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1137190 |
12/31/2022 |
Deficient Reporting |
4Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of December 2022. |
|
Violation |
B |
Report |
1137193 |
12/31/2022 |
Deficient Reporting |
4Q2022; Failure to report the following annual constituents for the land application area: Total Dissolved Solids Loading Rate and Fixed Dissolved Solids Loading Rate. |
|
Violation |
B |
Report |
1137192 |
12/31/2022 |
Deficient Reporting |
4Q2022; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of December 2022. |
|
Violation |
B |
Report |
1137189 |
11/30/2022 |
Deficient Reporting |
4Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of November 2022. |
|
Violation |
B |
Report |
1137191 |
11/30/2022 |
Deficient Reporting |
4Q2022; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr,, for the month of November 2022. |
|
Violation |
B |
Report |
1137170 |
11/28/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Chloride of effluent during the week of 11/28/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137182 |
11/28/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Fecal Coliform of effluent during the week of 11/28/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137165 |
11/28/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 11/28/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137187 |
11/28/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Total Coliform of effluent during the week of 11/28/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137169 |
11/21/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Chloride of effluent during the week of 11/21/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137181 |
11/21/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Fecal Coliform of effluent during the week of 11/21/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137164 |
11/21/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 11/21/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137186 |
11/21/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Total Coliform of effluent during the week of 11/21/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137168 |
11/14/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Chloride of effluent during the week of 11/14/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137180 |
11/14/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Fecal Coliform of effluent during the week of 11/14/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137163 |
11/14/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 11/14/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137185 |
11/14/2022 |
DMON |
ENTERED IN ERROR - 4Q2022; Failure to monitor Total Coliform of effluent during the week of 11/14/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1119867 |
11/10/2022 |
CAT1 |
Nitrate, Total (as N) Single Sample Maximum limit is 10 mg/L and reported value was 70.4 mg/L. |
|
Violation |
B |
Report |
1119866 |
11/10/2022 |
CAT1 |
Nitrite, Total (as N) Single Sample Maximum limit is 1 mg/L and reported value was 1.06 mg/L. |
|
Violation |
B |
Report |
1137173 |
11/07/2022 |
DMON |
4Q2022; Failure to monitor Boron of effluent during the week of 11/7/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137167 |
11/07/2022 |
DMON |
4Q2022; Failure to monitor Chloride of effluent during the week of 11/7/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137179 |
11/07/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform of effluent during the week of 11/7/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137162 |
11/07/2022 |
DMON |
4Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 11/7/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137176 |
11/07/2022 |
DMON |
4Q2022; Failure to monitor Surfactants of effluent during the week of 11/7/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137184 |
11/07/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform of effluent during the week of 11/7/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1119864 |
11/03/2022 |
OEV |
Fecal Coliform 1-Hour Average (Mean) limit is 2.2 MPN/100 mL and reported value was 1600 MPN/100 mL. |
|
Violation |
B |
Report |
1119865 |
11/03/2022 |
OEV |
Total Coliform Single Sample Maximum limit is 2.2 MPN/100 mL and reported value was 2419.6 MPN/100 mL. |
|
Violation |
B |
Report |
1119862 |
11/03/2022 |
CAT1 |
Chloride Single Sample Maximum limit is 110 mg/L and reported value was 130 mg/L. |
|
Violation |
B |
Report |
1119861 |
11/03/2022 |
CAT1 |
Fixed Dissolved Solids (FDS) Single Sample Maximum limit is 1500 mg/L and reported value was 1690 mg/L. |
|
Violation |
B |
Report |
1119860 |
11/03/2022 |
CAT1 |
Nitrate, Total (as N) Single Sample Maximum limit is 10 mg/L and reported value was 53 mg/L. |
|
Violation |
B |
Report |
1119859 |
11/03/2022 |
CAT1 |
Nitrite, Total (as N) Single Sample Maximum limit is 1 mg/L and reported value was 1.36 mg/L. |
|
Violation |
B |
Report |
1136479 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136448 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136452 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136456 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136460 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136467 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136470 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136474 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136477 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Boron in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136446 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136466 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Chloride in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136468 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Color in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136471 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Color in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136475 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Color in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136441 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Odor in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136461 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Odor in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136472 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Odor in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136439 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136445 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136450 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136455 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136459 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136464 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Sulfate in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136442 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136453 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136438 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136478 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136443 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136449 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136454 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136457 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136462 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136469 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136473 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136476 |
10/31/2022 |
DMON |
4Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1137188 |
10/31/2022 |
Deficient Reporting |
4Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of October 2022. |
|
Violation |
B |
Report |
1119858 |
10/27/2022 |
CAT1 |
Nitrate, Total (as N) Single Sample Maximum limit is 10 mg/L and reported value was 45 mg/L. |
|
Violation |
B |
Report |
1119857 |
10/27/2022 |
CAT1 |
Nitrite, Total (as N) Single Sample Maximum limit is 1 mg/L and reported value was 1.2 mg/L. |
|
Violation |
B |
Report |
1137172 |
10/24/2022 |
DMON |
4Q2022; Failure to monitor Boron of effluent during the week of 10/24/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137166 |
10/24/2022 |
DMON |
4Q2022; Failure to monitor Chloride of effluent during the week of 10/24/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137178 |
10/24/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform of effluent during the week of 10/24/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137161 |
10/24/2022 |
DMON |
4Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 10/24/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137175 |
10/24/2022 |
DMON |
4Q2022; Failure to monitor Surfactants of effluent during the week of 10/24/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137183 |
10/24/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform of effluent during the week of 10/24/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1119856 |
10/20/2022 |
CAT1 |
Nitrate, Total (as N) Single Sample Maximum limit is 10 mg/L and reported value was 22 mg/L. |
|
Violation |
B |
Report |
1137171 |
10/17/2022 |
DMON |
4Q2022; Failure to monitor Boron of effluent during the week of 10/17/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136359 |
10/17/2022 |
DMON |
4Q2022; Failure to monitor Chloride of effluent during the week of 10/17/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137177 |
10/17/2022 |
DMON |
4Q2022; Failure to monitor Fecal Coliform of effluent during the week of 10/17/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136356 |
10/17/2022 |
DMON |
4Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 10/17/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1137174 |
10/17/2022 |
DMON |
4Q2022; Failure to monitor Surfactants of effluent during the week of 10/17/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136362 |
10/17/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform of effluent during the week of 10/17/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1119854 |
10/13/2022 |
OEV |
Fecal Coliform Single Sample Maximum limit is 2.2 MPN/100 mL and reported value was 2419.6 MPN/100 mL. |
|
Violation |
B |
Report |
1119855 |
10/13/2022 |
OEV |
Total Coliform Single Sample Maximum limit is 2.2 MPN/100 mL and reported value was 2419.6 MPN/100 mL. |
|
Violation |
B |
Report |
1119852 |
10/13/2022 |
CAT1 |
Boron, Total Single Sample Maximum limit is 1 mg/L and reported value was 1.73 mg/L. |
|
Violation |
B |
Report |
1119851 |
10/13/2022 |
CAT1 |
Chloride Single Sample Maximum limit is 110 mg/L and reported value was 120 mg/L. |
|
Violation |
B |
Report |
1119850 |
10/13/2022 |
CAT1 |
Fixed Dissolved Solids (FDS) Single Sample Maximum limit is 1500 mg/L and reported value was 1550 mg/L. |
|
Violation |
B |
Report |
1119853 |
10/13/2022 |
CAT1 |
Methylene Blue Active Substances (MBAS) Single Sample Maximum limit is 0.5 mg/L and reported value was 0.71 mg/L. |
|
Violation |
B |
Report |
1136358 |
10/10/2022 |
DMON |
4Q2022; Failure to monitor Chloride of effluent during the week of 10/10/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136355 |
10/10/2022 |
DMON |
4Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 10/10/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136361 |
10/10/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform of effluent during the week of 10/10/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136357 |
10/03/2022 |
DMON |
4Q2022; Failure to monitor Chloride of effluent during the week of 10/3/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136354 |
10/03/2022 |
DMON |
4Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 10/3/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136360 |
10/03/2022 |
DMON |
4Q2022; Failure to monitor Total Coliform of effluent during the week of 10/3/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136421 |
09/30/2022 |
DMON |
3Q2022; EPA 300 for Chloride has a maximum holding time of 28 days. Sulfate has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-8 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136306 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136434 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136235 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136391 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136241 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136394 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136250 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136398 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136258 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136401 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136270 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136410 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136280 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136415 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136290 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136423 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136298 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136430 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136304 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136233 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136390 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136256 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136268 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136405 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136278 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136288 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136411 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Color in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136416 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Color in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136292 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Color in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136424 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Color in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136377 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136386 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136378 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136379 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136380 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136381 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136382 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136383 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136384 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136385 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136316 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136347 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform of effluent monthly as required by the MRP during the month of September. |
|
Violation |
B |
Report |
1136387 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Odor in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136260 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Odor in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136402 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Odor in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136282 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Odor in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136417 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Odor in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136225 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136366 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136302 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136231 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136239 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136393 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136248 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136397 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136254 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136400 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136266 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136404 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136276 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136286 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136296 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136308 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Surfactants in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136227 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136388 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136310 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136243 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136395 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136262 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136272 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136223 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136363 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136364 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136300 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136431 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136229 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136389 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136237 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136392 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136246 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136396 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136252 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136399 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136264 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136403 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136274 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136412 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136284 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136418 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136425 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136294 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136426 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136367 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136376 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136368 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136369 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136370 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136371 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136372 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136373 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136374 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136375 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136315 |
09/30/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136319 |
09/30/2022 |
Deficient Reporting |
3Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of September 2022. |
|
Violation |
B |
Report |
1136321 |
09/30/2022 |
Deficient Reporting |
3Q2022; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of September 2022. |
|
Violation |
B |
Report |
1136332 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Ammonia as Nitrogen of effluent weekly as required by the MRP during the week of 9/26/2022. |
|
Violation |
B |
Report |
1136339 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Chloride of effluent during the week of 9/26/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136346 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform of effluent during the week of 9/26/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136325 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 9/26/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136331 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Nitrate as Nitrogen of effluent weekly as required by the MRP during the week of 9/26/2022. |
|
Violation |
B |
Report |
1136333 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Nitrite as Nitrogen of effluent weekly as required by the MRP during the week of 9/26/2022. |
|
Violation |
B |
Report |
1136334 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Organic Nitrogen of effluent weekly as required by the MRP during the week of 9/26/2022. |
|
Violation |
B |
Report |
1136351 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform of effluent during the week of 9/26/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136335 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor Total Nitrogen of effluent weekly as required by the MRP during the week of 9/26/2022. |
|
Violation |
B |
Report |
1136353 |
09/26/2022 |
DMON |
3Q2022; Failure to monitor pH of effluent weekly as required by the MRP during the week of 9/26/2022. |
|
Violation |
B |
Report |
1136352 |
09/22/2022 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 2419.6 MPN/100 mL. |
|
Violation |
B |
Report |
1136341 |
09/22/2022 |
CAT1 |
Chloride Daily Maximum limit is 110 mg/L and reported value was 140 mg/L. |
|
Violation |
B |
Report |
1136326 |
09/22/2022 |
CAT1 |
Fixed Dissolved Solids (FDS) Daily Maximum limit is 1500 mg/L and reported value was 1550 mg/L. |
|
Violation |
B |
Report |
1136345 |
09/19/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform of effluent during the week of 9/19/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136338 |
09/12/2022 |
DMON |
3Q2022; Failure to monitor Chloride of effluent during the week of 9/12/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136344 |
09/12/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform of effluent during the week of 9/12/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136324 |
09/12/2022 |
DMON |
3Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 9/12/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136350 |
09/12/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform of effluent during the week of 9/12/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136337 |
09/05/2022 |
DMON |
3Q2022; Failure to monitor Chloride of effluent during the week of 9/5/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136343 |
09/05/2022 |
DMON |
3Q2022; Failure to monitor Fecal Coliform of effluent during the week of 9/5/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136323 |
09/05/2022 |
DMON |
3Q2022; Failure to monitor Fixed Dissolved Solids of effluent during the week of 9/5/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136349 |
09/05/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform of effluent during the week of 9/5/2022 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1136318 |
08/31/2022 |
Deficient Reporting |
3Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of August 2022. |
|
Violation |
B |
Report |
1136320 |
08/31/2022 |
Deficient Reporting |
3Q2022; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of August 2022. |
|
Violation |
B |
Report |
1136342 |
08/31/2022 |
OEV |
Fecal Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 1600 MPN/100 mL. |
|
Violation |
B |
Report |
1136348 |
08/31/2022 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 1600 MPN/100 mL. |
|
Violation |
B |
Report |
1136336 |
08/31/2022 |
CAT1 |
Chloride Daily Maximum limit is 110 mg/L and reported value was 130 mg/L. |
|
Violation |
B |
Report |
1136322 |
08/31/2022 |
CAT1 |
Fixed Dissolved Solids (FDS) Daily Maximum limit is 1500 mg/L and reported value was 1510 mg/L. |
|
Violation |
B |
Report |
1136330 |
08/31/2022 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 16 mg/L. |
|
Violation |
B |
Report |
1136329 |
08/25/2022 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 30 mg/L. |
|
Violation |
B |
Report |
1136328 |
08/18/2022 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 55 mg/L. |
|
Violation |
B |
Report |
1136327 |
08/12/2022 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 89 mg/L. |
|
Violation |
B |
Report |
1136365 |
08/02/2022 |
OEV |
pH Instantaneous Minimum limit is 6.5 SU and reported value was 6.3 SU. |
|
Violation |
B |
Report |
1136433 |
08/01/2022 |
Deficient Reporting |
3Q2022; EPA 300 for Chloride has a maximum holding time of 28 days. Chloride has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-10 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136414 |
08/01/2022 |
Deficient Reporting |
3Q2022; EPA 300 for Chloride has a maximum holding time of 28 days. Chloride has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-7 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136422 |
08/01/2022 |
Deficient Reporting |
3Q2022; EPA 300 for Chloride has a maximum holding time of 28 days. Chloride has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-8 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136428 |
08/01/2022 |
Deficient Reporting |
3Q2022; EPA 300 for Chloride has a maximum holding time of 28 days. Chloride has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-9 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136432 |
08/01/2022 |
Deficient Reporting |
3Q2022; EPA 300 for Sulfate has a maximum holding time of 28 days. Sulfate has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-10 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136413 |
08/01/2022 |
Deficient Reporting |
3Q2022; EPA 300 for Sulfate has a maximum holding time of 28 days. Sulfate has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-7 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136419 |
08/01/2022 |
Deficient Reporting |
3Q2022; EPA 300 for Sulfate has a maximum holding time of 28 days. Sulfate has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-8 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136427 |
08/01/2022 |
Deficient Reporting |
3Q2022; EPA 300 for Sulfate has a maximum holding time of 28 days. Sulfate has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-9 was analyzed after the 28 day holding time limit elapsed. |
|
Violation |
B |
Report |
1136407 |
08/01/2022 |
Deficient Reporting |
3Q2022; SM 4500NO3-F for Nitrite as Nitrogen has a maximum holding time of 48 hours. Nitrite as Nitrogen has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-6 was analyzed after the 48 hour holding time limit elapsed. |
|
Violation |
B |
Report |
1136429 |
08/01/2022 |
Deficient Reporting |
3Q2022; SM 4500No3F for Nitrite as Nitrogen has a maximum holding time of 48 hours. Nitrite as Nitrogen has a quarterly reporting requirement and the sample taken on 8/1/2022 for MW-9 was analyzed after the 48 hour holding time limit elapsed. |
|
Violation |
B |
Report |
1136305 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136234 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-2 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136240 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-3 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136249 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136257 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136269 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136279 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136289 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136297 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Boron in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136303 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136232 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-2 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136255 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136267 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136277 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136287 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Chloride in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136291 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Color in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136259 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Odor in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136281 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Odor in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136224 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-1 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136301 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136230 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-2 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136238 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-3 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136247 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136253 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136265 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136275 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136285 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136295 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Sulfate in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136307 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Surfactants in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136226 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-1 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136309 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136242 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-3 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136261 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136271 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Coliform in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136222 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136299 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136228 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-2 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136236 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-3 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136244 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136245 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-4 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136251 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136263 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136273 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136283 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136293 |
07/31/2022 |
DMON |
3Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of July as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1136317 |
07/31/2022 |
Deficient Reporting |
3Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of July 2022. |
|
Violation |
B |
Report |
1136196 |
07/30/2022 |
Deficient Reporting |
2Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of April 2022. |
|
Violation |
B |
Report |
1136198 |
07/30/2022 |
Deficient Reporting |
2Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of June 2022. |
|
Violation |
B |
Report |
1136197 |
07/30/2022 |
Deficient Reporting |
2Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of May 2022. |
|
Violation |
B |
Report |
1136194 |
07/30/2022 |
Deficient Reporting |
2Q2022; Failure to report daily observations of the disposal area for the production plant OWTS. |
|
Violation |
B |
Report |
1136195 |
07/30/2022 |
Deficient Reporting |
2Q2022; Failure to report daily observations of the disposal area for the warehouse OWTS. |
|
Violation |
B |
Report |
1136212 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136221 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136213 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136214 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136215 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136216 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136217 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136218 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136219 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136220 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136201 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136202 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136211 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136203 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136204 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136205 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136206 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136207 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136208 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136209 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136210 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1136200 |
06/30/2022 |
DMON |
2Q2022; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135961 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-10 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135911 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-5 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135921 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-6 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135931 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-7 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135943 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-8 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135951 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-9 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135959 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-10 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135891 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-2 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135909 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-5 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135919 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-6 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135929 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-7 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135941 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-8 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135893 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Color in MW-2 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135945 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Color in MW-8 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135883 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Nitrate as Nitrogen in MW-1 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135903 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Nitrate as Nitrogen in MW-4 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135913 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Odor in MW-5 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135933 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Odor in MW-7 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135881 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-1 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135957 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-10 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135889 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-2 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135897 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-3 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135901 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-4 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135907 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-5 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135917 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-6 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135927 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-7 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135939 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-8 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135949 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-9 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135885 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-1 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135963 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-10 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135895 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-2 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135899 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-3 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135923 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-6 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135935 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-7 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135953 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-9 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135878 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135955 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135887 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-2 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135905 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135915 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135925 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135937 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135947 |
05/31/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of May as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135960 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135910 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135920 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135930 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135942 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135950 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Boron in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135958 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135890 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135908 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135918 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135928 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135940 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Chloride in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135892 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Color in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135944 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Color in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135882 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Nitrate as Nitrogen in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135902 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Nitrate as Nitrogen in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135912 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Odor in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135932 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Odor in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135879 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135956 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135888 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135896 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-3 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135900 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-4 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135906 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135916 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135926 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135938 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135948 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Sulfate in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135884 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135962 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135894 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135898 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-3 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135922 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135934 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135952 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Coliform in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135877 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135954 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135886 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-2 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135904 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135914 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135924 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135936 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135946 |
04/30/2022 |
DMON |
2Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of April as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135856 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135874 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135858 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135860 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135862 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135864 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135866 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135868 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135870 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135872 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135876 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135855 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135873 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135857 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135859 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135861 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135863 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135865 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135867 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135869 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135871 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135875 |
03/31/2022 |
DMON |
1Q2022; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135851 |
03/31/2022 |
DMON |
1Q2022; Failure to report daily observations of the disposal area for the warehouse OWTS. |
|
Violation |
B |
Report |
1135734 |
03/31/2022 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135854 |
03/31/2022 |
Deficient Reporting |
1Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of March 2022. |
|
Violation |
B |
Report |
1135850 |
03/31/2022 |
Deficient Reporting |
1Q2022; Failure to report daily observations of the disposal area for the production plant OWTS. |
|
Violation |
B |
Report |
1135721 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135835 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135748 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135762 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135772 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135784 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135798 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135812 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135824 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135834 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135733 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135770 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135782 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135796 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135810 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135822 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135841 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Color in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135739 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Color in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135815 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Color in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135753 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Odor in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135775 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Odor in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135803 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Odor in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135719 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135832 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135731 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135746 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135760 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135768 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135780 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135794 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135808 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135820 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135839 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135736 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135751 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135787 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135801 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135726 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135742 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135756 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135790 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135828 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135717 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135830 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135728 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-2 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135744 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-3 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135758 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-4 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135766 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135778 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135792 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135806 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135818 |
02/28/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of February as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135853 |
02/28/2022 |
Deficient Reporting |
1Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of February 2022. |
|
Violation |
B |
Report |
1135720 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135836 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135747 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135761 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135771 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135783 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135797 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135811 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135823 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Boron in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135833 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135732 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135769 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135781 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135795 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135809 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135821 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Chloride in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135840 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Color in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135738 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Color in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135814 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Color in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135752 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Odor in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135774 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Odor in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135802 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Odor in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135718 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135831 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135730 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135745 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135759 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135767 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135779 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135793 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135807 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135819 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Sulfate in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135838 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135735 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135750 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135786 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135800 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Surfactants in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135725 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135741 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135755 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135789 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135827 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Coliform in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135716 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-1 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135829 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-10 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135727 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-2 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135743 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-3 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135757 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-4 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135765 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-5 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135777 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-6 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135791 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-7 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135805 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-8 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135817 |
01/31/2022 |
DMON |
1Q2022; Failure to monitor Total Dissolved Solids in MW-9 during the month of January as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135852 |
01/31/2022 |
Deficient Reporting |
1Q2022; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of January 2022. |
|
Violation |
B |
Report |
1135712 |
01/31/2022 |
Deficient Reporting |
4Q2021; Failure to include the observation log of the land application area as required by the MRP. |
|
Violation |
B |
Report |
1135704 |
01/31/2022 |
Deficient Reporting |
4Q2021; Failure to report daily observations of the disposal area for the production plant OWTS. |
|
Violation |
B |
Report |
1135705 |
01/31/2022 |
Deficient Reporting |
4Q2021; Failure to report daily observations of the disposal area for the warehouse OWTS. |
|
Violation |
B |
Report |
1135711 |
01/31/2022 |
Deficient Reporting |
4Q2021; Failure to report the following annual constituents for the land application area: Total Dissolved Solids Loading Rate and Fixed Dissolved Solids Loading Rate in lb/acre/year. |
|
Violation |
B |
Report |
1135849 |
01/31/2022 |
Deficient Reporting |
Failure to report the following for the office OWTS: name and address of the party responsible for operation and maintenance, frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1135847 |
01/31/2022 |
Deficient Reporting |
Failure to report the following for the production plant OWTS: name and address of the party responsible for operation and maintenance, frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1135848 |
01/31/2022 |
Deficient Reporting |
Failure to report the following for the warehouse OWTS: name and address of the party responsible for operation and maintenance frequency of maintenance, any pumping, and maintenance records. |
|
Violation |
B |
Report |
1135724 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135842 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135740 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135754 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135764 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135776 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135788 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135804 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135816 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135826 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135845 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135723 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135837 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135737 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135749 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135763 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135773 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135785 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135799 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135813 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135825 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135844 |
12/31/2021 |
DMON |
4Q2021; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135708 |
12/31/2021 |
Deficient Reporting |
4Q2021; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of December 2021. |
|
Violation |
B |
Report |
1135843 |
12/08/2021 |
DMON |
4Q2021; Standard Method 4500-H+B for pH has a maximum holding time of 15 minutes, and the sample taken on 12/8/2021 was analyzed after the 15 minute holding time limit elapsed. |
|
Violation |
B |
Report |
1135277 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-1 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135650 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-10 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135308 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-3 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135325 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-4 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135372 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-6 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135403 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-7 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135425 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-8 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135442 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-9 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135274 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-1 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135647 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-10 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135294 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-2 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135343 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-5 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135367 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-6 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135399 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-7 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135422 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-8 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135656 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Color in MW-10 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135429 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Color in MW-8 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135446 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Color in MW-9 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135695 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in effluent monthly as required by the MRP. |
|
Violation |
B |
Report |
1135281 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Odor in MW-1 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135313 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Odor in MW-3 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135351 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Odor in MW-5 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135408 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Odor in MW-7 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135271 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-1 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135644 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-10 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135291 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-2 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135305 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-3 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135322 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-4 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135339 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-5 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135363 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-6 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135396 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-7 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135419 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-8 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135439 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-9 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135285 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-1 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135660 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-10 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135299 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-2 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135316 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-3 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135330 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-4 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135358 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-5 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135387 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-6 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135413 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-7 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135433 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-8 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135450 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-9 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135268 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-1 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135641 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-10 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135288 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-2 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135302 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-3 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135319 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-4 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135335 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-5 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135391 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-7 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135416 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-8 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135436 |
11/30/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-9 during the month of November as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135707 |
11/30/2021 |
Deficient Reporting |
4Q2021; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of November 2021. |
|
Violation |
B |
Report |
1135710 |
11/30/2021 |
Deficient Reporting |
4Q2021; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of November 2021. |
|
Violation |
B |
Report |
1135688 |
11/29/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Boron of effluent during the week of 11/29/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135680 |
11/29/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Chloride of effluent during the week of 11/29/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135670 |
11/29/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 11/29/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135693 |
11/29/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Surfactants of effluent during the week of 11/29/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135703 |
11/29/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Total Coliform of effluent during the week of 11/29/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135687 |
11/22/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Boron of effluent during the week of 11/22/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135679 |
11/22/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Chloride of effluent during the week of 11/22/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135669 |
11/22/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 11/22/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135692 |
11/22/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Surfactants of effluent during the week of 11/22/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135702 |
11/22/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Total Coliform of effluent during the week of 11/22/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135686 |
11/15/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Boron of effluent during the week of 11/15/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135678 |
11/15/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Chloride of effluent during the week of 11/15/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135668 |
11/15/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 11/15/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135691 |
11/15/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Surfactants of effluent during the week of 11/15/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135701 |
11/15/2021 |
DMON |
ENTERED IN ERROR - 4Q2021; Failure to monitor Total Coliform of effluent during the week of 11/15/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135684 |
11/08/2021 |
DMON |
4Q2021; Failure to monitor Boron of effluent during the week of 11/8/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135676 |
11/08/2021 |
DMON |
4Q2021; Failure to monitor Chloride of effluent during the week of 11/8/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135666 |
11/08/2021 |
DMON |
4Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 11/8/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135690 |
11/08/2021 |
DMON |
4Q2021; Failure to monitor Surfactants of effluent during the week of 11/8/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135699 |
11/08/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform of effluent during the week of 11/8/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135700 |
11/05/2021 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 24000 MPN/100 mL. |
|
Violation |
B |
Report |
1135685 |
11/05/2021 |
CAT1 |
Boron, Total Daily Maximum limit is 1 mg/L and reported value was 2.58 mg/L. |
|
Violation |
B |
Report |
1135677 |
11/05/2021 |
CAT1 |
Chloride Daily Maximum limit is 110 mg/L and reported value was 160 mg/L. |
|
Violation |
B |
Report |
1135667 |
11/05/2021 |
CAT1 |
Fixed Dissolved Solids (FDS) Daily Maximum limit is 1500 mg/L and reported value was 1660 mg/L. |
|
Violation |
B |
Report |
1135689 |
11/05/2021 |
CAT1 |
Methylene Blue Active Substances (MBAS) Daily Maximum limit is .5 mg/L and reported value was .536 mg/L. |
|
Violation |
B |
Report |
1135276 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135649 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135307 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135324 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135370 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135402 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135424 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135441 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Boron in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135273 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135646 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135293 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135342 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135365 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135398 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135421 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Chloride in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135655 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Color in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135428 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Color in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135445 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Color in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135694 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Fecal Coliform in effluent monthly as required by the MRP. |
|
Violation |
B |
Report |
1135280 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Odor in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135312 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Odor in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135350 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Odor in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135407 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Odor in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135270 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135643 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135290 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135304 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135321 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135338 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135360 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135395 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135418 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135438 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Sulfate in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135284 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135659 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135298 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135315 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135329 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135356 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135386 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-6 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135412 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135432 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135449 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135267 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-1 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135452 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-10 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135287 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-2 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135301 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-3 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135318 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-4 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135334 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-5 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135390 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-7 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135415 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-8 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135435 |
10/31/2021 |
DMON |
4Q2021; Failure to monitor Total Dissolved Solids in MW-9 during the month of October as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135265 |
10/31/2021 |
Deficient Reporting |
3Q2021; Failure to include the observation log of the land application area as required by the MRP. |
|
Violation |
B |
Report |
1135260 |
10/31/2021 |
Deficient Reporting |
3Q2021; Failure to report daily observations of the disposal area for the office OWTS. |
|
Violation |
B |
Report |
1135255 |
10/31/2021 |
Deficient Reporting |
3Q2021; Failure to report daily observations of the disposal area for the warehouse OWTS. |
|
Violation |
B |
Report |
1135254 |
10/31/2021 |
Deficient Reporting |
3Q2021; Failure to report the daily observations of the disposal area for the production plant OWTS. |
|
Violation |
B |
Report |
1135706 |
10/31/2021 |
Deficient Reporting |
4Q2021; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of October 2021. |
|
Violation |
B |
Report |
1135709 |
10/31/2021 |
Deficient Reporting |
4Q2021; Failure to report the following monthly constituents for the land application area: Application Area, BOD Loading Rate, Total Nitrogen Loading Rate, Runoff, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of October 2021. |
|
Violation |
B |
Report |
1135683 |
10/25/2021 |
DMON |
4Q2021; Failure to monitor Boron of effluent during the week of 10/25/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135675 |
10/25/2021 |
DMON |
4Q2021; Failure to monitor Chloride of effluent during the week of 10/25/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135665 |
10/25/2021 |
DMON |
4Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 10/25/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135698 |
10/25/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform of effluent during the week of 10/25/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135682 |
10/18/2021 |
DMON |
4Q2021; Failure to monitor Boron of effluent during the week of 10/18/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135674 |
10/18/2021 |
DMON |
4Q2021; Failure to monitor Chloride of effluent during the week of 10/18/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135664 |
10/18/2021 |
DMON |
4Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 10/18/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135697 |
10/18/2021 |
DMON |
4Q2021; Failure to monitor Total Coliform of effluent during the week of 10/18/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135696 |
10/15/2021 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 24000 MPN/100 mL. |
|
Violation |
B |
Report |
1135681 |
10/15/2021 |
CAT1 |
Boron, Total Daily Maximum limit is 1 mg/L and reported value was 1.52 mg/L. |
|
Violation |
B |
Report |
1135673 |
10/15/2021 |
CAT1 |
Chloride Daily Maximum limit is 110 mg/L and reported value was 130 mg/L. |
|
Violation |
B |
Report |
1135663 |
10/15/2021 |
CAT1 |
Fixed Dissolved Solids (FDS) Daily Maximum limit is 1500 mg/L and reported value was 1590 mg/L. |
|
Violation |
B |
Report |
1135671 |
10/01/2021 |
DMON |
4Q2021; Failure to monitor Nitrate as Nitrogen in effluent weekly as required by the MRP. |
|
Violation |
B |
Report |
1135672 |
10/01/2021 |
DMON |
4Q2021; Failure to monitor Nitrite as Nitrogen in effluent weekly as required by the MRP. |
|
Violation |
B |
Report |
1135275 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Boron in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135648 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Boron in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135306 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Boron in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135323 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Boron in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135368 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Boron in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135400 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Boron in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135423 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Boron in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135440 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Boron in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135272 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Chloride in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135645 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Chloride in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135292 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Chloride in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135340 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Chloride in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135364 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Chloride in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135397 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Chloride in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135420 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Chloride in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135654 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Color in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135427 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Color in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135444 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Color in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135282 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135657 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135296 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135314 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135327 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135353 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135384 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135409 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135430 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135447 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135662 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135247 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform of effluent monthly as required by the MRP during the month of September 2021. |
|
Violation |
B |
Report |
1135279 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Odor in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135310 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Odor in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135348 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Odor in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135405 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Odor in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135269 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135642 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135289 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135303 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135320 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135337 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135359 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135392 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135417 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135437 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Sulfate in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135283 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135658 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135297 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135311 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135328 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135355 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135385 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-6 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135411 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135431 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135448 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135266 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-1 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135451 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-10 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135286 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-2 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135300 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-3 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135317 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-4 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135333 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-5 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135389 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-7 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135414 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-8 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135434 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Dissolved Solids in MW-9 during the month of September as required by the MRP. If the quarterly monitoring test results exceed the groundwater limitations, the monitoring frequency shall be monthly, for at least 3 consecutive months. |
|
Violation |
B |
Report |
1135278 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-1 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135653 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-10 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135295 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-2 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135309 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-3 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135326 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-4 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135344 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-5 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135374 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-6 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135404 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-7 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135426 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-8 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135443 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in MW-9 quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135661 |
09/30/2021 |
DMON |
3Q2021; Failure to monitor Total Nitrogen in the Supply Wells quarterly as required by the MRP. |
|
Violation |
B |
Report |
1135259 |
09/30/2021 |
Deficient Reporting |
3Q2021; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of September 2021. |
|
Violation |
B |
Report |
1135264 |
09/30/2021 |
Deficient Reporting |
3Q2021; Failure to report the following monthly constituents for the land application area: BOD Loading Rate, Total Nitrogen Loading Rate, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of September 2021. |
|
Violation |
B |
Report |
1135262 |
09/30/2021 |
Deficient Reporting |
3Q2021; Failure to report the land application area for the month of September 2021 as required by the MRP. |
|
Violation |
B |
Report |
1135252 |
09/27/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform of effluent during the week of 9/27/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135245 |
09/20/2021 |
DMON |
3Q2021; Failure to monitor Chloride of effluent during the week of 9/20/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135227 |
09/20/2021 |
DMON |
3Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 9/20/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135251 |
09/20/2021 |
DMON |
3Q2021; Failure to monitor Toal Coliform of effluent during the week of 9/20/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135244 |
09/13/2021 |
DMON |
3Q2021; Failure to monitor Chloride of effluent during the week of 9/13/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135226 |
09/13/2021 |
DMON |
3Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 9/13/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135250 |
09/13/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform of effluent during the week of 9/13/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135234 |
09/10/2021 |
CAT1 |
Nitrite, Total (as N) Daily Maximum limit is 1 mg/L and reported value was 3.3 mg/L. |
|
Violation |
B |
Report |
1135243 |
09/06/2021 |
DMON |
3Q2021; Failure to monitor Chloride of effluent during the week of 9/6/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135225 |
09/06/2021 |
DMON |
3Q2021; Failure to monitor Fixed Dissolved Solids of effluent during the week of 9/6/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135249 |
09/06/2021 |
DMON |
3Q2021; Failure to monitor Total Coliform of effluent during the week of 9/6/2021 as required by the MRP. If the monthly monitoring test results exceed the effluent limitations, the monitoring frequency shall be weekly, for at least 4 consecutive weeks. |
|
Violation |
B |
Report |
1135246 |
08/31/2021 |
DMON |
3Q2021; Failure to monitor Fecal Coliform of effluent monthly as required by the MRP during the month of August 2021. |
|
Violation |
B |
Report |
1135258 |
08/31/2021 |
Deficient Reporting |
3Q2021; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of August 2021. |
|
Violation |
B |
Report |
1135263 |
08/31/2021 |
Deficient Reporting |
3Q2021; Failure to report the following monthly constituents for the land application area: BOD Loading Rate, Total Nitrogen Loading Rate, Wastewater Loading Rate in both gpd and in/d, Precipitation Loading Rate, Evaporation Loading Rate, and Total Hydraulic Loading rate in both in/d and in/hr, for the month of August 2021. |
|
Violation |
B |
Report |
1135261 |
08/31/2021 |
Deficient Reporting |
3Q2021; Failure to report the land application area for the month of August 2021 as required by the MRP. |
|
Violation |
B |
Report |
1135248 |
08/27/2021 |
OEV |
Total Coliform Daily Maximum limit is 2.2 MPN/100 mL and reported value was 24196 MPN/100 mL. |
|
Violation |
B |
Report |
1135235 |
08/27/2021 |
CAT1 |
Chloride Daily Maximum limit is 110 mg/L and reported value was 130 mg/L. |
|
Violation |
B |
Report |
1135228 |
08/27/2021 |
CAT1 |
Fixed Dissolved Solids (FDS) Daily Maximum limit is 1500 mg/L and reported value was 1610 mg/L. |
|
Violation |
B |
Report |
1135231 |
08/27/2021 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 34 mg/L. |
|
Violation |
B |
Report |
1135230 |
08/20/2021 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 110 mg/L. |
|
Violation |
B |
Report |
1135233 |
08/20/2021 |
CAT1 |
Nitrite, Total (as N) Daily Maximum limit is 1 mg/L and reported value was 2.1 mg/L. |
|
Violation |
B |
Report |
1135229 |
08/13/2021 |
CAT1 |
Nitrate, Total (as N) Daily Maximum limit is 10 mg/L and reported value was 630 mg/L. |
|
Violation |
B |
Report |
1135232 |
08/13/2021 |
CAT1 |
Nitrite, Total (as N) Daily Maximum limit is 1 mg/L and reported value was 1.49 mg/L. |
|
Violation |
B |
Report |
1135257 |
07/31/2021 |
Deficient Reporting |
3Q2021; Failure to report all monthly constituents for the office OWTS, including average daily flow, maximum daily flow, average water usage rate, and estimated population served for the month of July 2021. |
|
Violation |
B |
Report |
Report displays most recent five years of violations. Refer to the Interactive Violation Report for more data.
|