Violation ID |
Occurred Date |
Violation Type |
(-) Violation Description |
Corrective Action |
Status |
Classification |
Source |
1124419 |
01/12/2024 |
CTOX |
Chronic Toxicity-Sea Urchin or Sand Dollar-Fertilization Event Discharge limit is 25 % effect and reported value was 98 % effect at M-2. |
As a result of this MDEL exceedance, NASSCO conducted a facility evaluation and assessment of current Best Management Practices (BMPs) and facility plans including the Graving Dock Undocking Procedure which describes the cleaning operations. The results of the investigation concluded current BMPs were properly implemented and operational. Additionally, Enthalpy Laboratories initiated a toxic identification evaluation (TIE) as directed by NASSCO. NASSCO is evaluating the results of the TIE as the results indicate there may be constituents other than metals causing toxicity. There were no other indicators, operations or possible pollutants identified that would have caused exceedance. |
Violation |
U |
eSMR |
1120843 |
08/22/2023 |
Surface Water |
On August 22, 2023, NASSCO Security was notified of a spill to San Diego Bay from the USNS Earl Warren (T-AO 3) at Berth 2. Approximately 1 gallon of oily storm water overflowed into the Bay from the flight deck TAO-3 mid ship. Due to the storm prediction for Hurricane Hillary, the vessel was not accessible causing storm water to overflow from the vessel deck. The incident resulted in a visible sheen approximately 20 x 40 feet in size. |
NASSCO employees immediately secured the source and pumped remaining storm water from the deck once vessel access was restored. Water Front Services (WFS) contained the spill within an oil boom. NASSCO followed all best management practices, however, the spill was not recoverable.
NASSCO notified the following agencies: National Response Center (NRC #1376900), Office of Emergency Services (OES #23-5362), U.S. Coast Guard, and the Regional Water Quality Control Board (RWQCB) (voicemail & notification letter). |
Violation |
U |
eSMR |
1119467 |
07/26/2023 |
Surface Water |
On July 26, 2023, an unknown amount of hydraulic oil spilled from a boomlift from a ruptured hose during startup. The boomlift was located on a test barge when the incident occurred resulting in a small amount of oil to reach San Diego Bay. NASSCO Security notified NASSCO Fire Department (NFD) and Environmental Engineering to respond.
|
NFD responded to secure and clean the spill on the barge, NASSCOs Waterfront Services Department contained the spill in the water with an oil boom. NASSCO contacted Republic Services (OSRO), upon arrival the OSRO deployed oil boom in the water, but the sheen in the Bay was not recoverable. All cleanup materials were collected and disposed as hazardous waste. NFD contacted United Rentals, equipment owner, to repair the equipment. |
Violation |
U |
eSMR |
1118660 |
06/29/2023 |
Surface Water |
On June 29, 2023, NASSCO employees were performing pipe flushing operations onboard a vessel when a gasket on the fuel strainer (filter unit) failed, resulting in approximately 100 gallons of diesel fuel to spill onto the vessel deck. Responders used absorbent pads to keep the majority of the spill to the vessel deck. However, an unknown amount (estimated less than 2 gallons) of material leaked through a plugged deck drain and into San Diego Bay resulting in a sheen of 30' by 5' on the water surface. NASSCO employees immediately secured the source of the spill, placed absorbent pads and materials on the deck, and blocked all deck drains to prevent further discharge. NASSCO also contacted our OSRO who responded to place an absorbent boom into the Bay.
This incident is an NPDES permit violation, NASSCO notified the following agencies: National Response Center, Office of Emergency Services, U.S. Coast Guard, and the Regional Water Quality Control Board (RWQCB). |
NASSCOs flushing crew reviewed and revised the flushing procedures to lower the operating pressure during flushing operations. Additionally, all deck drains will be plugged and blocked prior to flushing operations and filter strainer "O" rings will be monitored and changed more frequently during flushing. |
Violation |
U |
eSMR |
1118082 |
05/12/2023 |
Surface Water |
On May 12, 2023, a NASSCO Waterfront Services employee was checking the oil on skiff #3 when backpressure in the system caused oil to spurt out of the dipstick nozzle releasing approximately 3 oz. of oil into San Diego Bay. The release of oil into the Bay is a violation of NASSCO's NPDES Permit and reportable to US Coast Guard and Regional Water Quality Control Board. |
"Root Cause: Personnel was unprepared for potential discharge.
Corrective Actions: Conducted retraining with WFS employees and implemented additional BMPs, including rags are used to cover the opening and prevent a discharge. |
Violation |
U |
eSMR |
1113369 |
01/31/2023 |
Surface Water |
On January 31, 2023 at approx. 1040 hrs. NASSCO Security reported a sheen in San Diego Bay adjacent to a vessel located on NASSCO¿s Berth 5. NASSCO Fire Department (NFD), Test and Trials (TNT) and Environmental Engineering responded to the spill location. The initial investigation revealed approximately 4 gallons of JP-5 fuel spilled on the vessel main deck that entered an unsecured deck drain and leaked into San Diego Bay. The spill caused a rainbow sheen approximately 10¿ x 15¿ that was contained within the containment boom around the vessel. |
Employees immediately secured the spill and blocked the deck drain. NASSCO response team placed absorbent pads in the water, but the spill was non-recoverable.
NASSCO Environmental Engineering issued a corrective action request to the responsible party. However, the root cause investigation is on-going. |
Violation |
U |
eSMR |
1111389 |
12/21/2022 |
DMON |
Analysis of copper by EPA 1600 series methods could not be performed by due date for IX-1 and RW due to laboratory instrument failure. |
Contacted lab and awaiting repair of instrument. Partial lab report has been uploaded to CIWQS for other parameters. Final lab data will be transmitted to RWQCB once final results are received from lab. |
Violation |
U |
eSMR |
1106291 |
06/08/2022 |
Surface Water |
On June 8, 2022 at approx. 0829 hrs. NASSCO Security reported a sheen in San Diego Bay adjacent to a vessel located on NASSCO¿s Berth 5. NASSCO Fire Department (NFD) and Environmental Engineering responded to the spill location. The spill caused a thin rainbow sheen approximately 30¿ x 30¿ that was contained within the containment boom around the vessel. |
During the investigation, the sheen dissipated and was not recoverable. The investigation did not identify the source of the spill. All BMPs were reviewed and were properly implemented. |
Violation |
U |
eSMR |
1105961 |
05/16/2022 |
CTOX |
Chronic Toxicity Maximum Daily (MDEL) limit is 0 Pass/Fail (Pass = 0, Fail = 1) and reported value was 1 Pass/Fail (Pass = 0, Fail = 1) at M-2. |
As a result of this MDEL exceedance, NASSCO conducted a facility evaluation and assessment of current Best Management Practices (BMP¿s) and facility plans including the Graving Dock Undocking Procedure which describes the cleaning operations. The results of the investigation concluded current BMP¿s were properly implemented and fully operational. However, the reference sample collected from San Diego Bay also resulted in a MDEL exceedance for the same test species. There were no other indicators, operations or possible pollutants identified that would have caused exceedance. |
Violation |
U |
eSMR |
1100501 |
01/31/2022 |
LREP |
Monthly SMR ( MONRPT ) report for December 2021 (1865465) was due on 30-JAN-22 |
|
Violation |
B |
Report |
1100500 |
01/31/2022 |
LREP |
Semi-Annual SMR ( MONRPT ) report for H2 2021 (1865472) was due on 30-JAN-22 |
|
Violation |
B |
Report |
1099026 |
12/31/2021 |
LREP |
Monthly SMR ( MONRPT ) report for November 2021 (1865464) was due on 30-DEC-21 |
|
Violation |
B |
Report |
1096463 |
10/31/2021 |
LREP |
Quarterly SMR ( MONRPT ) report for Q3 2021 (1865469) was due on 30-OCT-21 |
|
Violation |
B |
Report |
1089853 |
04/14/2021 |
Surface Water |
On April 14, 2021 at 1122 hrs., NASSCO Security received a report of a 20 ft. x 20 ft. orange discoloration in the San Diego Bay near Pier 12, the discoloration was a result of dewatering a NASSCO barge that was moored at Pier 12. The barge dewatering was immediately secured once the operator became aware of the rust water and reported the incident. Approximately 50 gallons of rust water was discharged.
The incident is a prohibited discharge under NASSCO's NPDES permit. However, the discharge did not exceed a Reportable Quantity (RQ) and did not endanger health or the environment.
|
The operators will inspect the barge tanks prior to any future dewatering operations to prevent reoccurrence. |
Violation |
U |
eSMR |
1089156 |
03/09/2021 |
Surface Water |
On March 9, 2021 at approx. 1920 hrs., NASSCO Security was notified of a hydraulic oil spill to San Diego Bay from a Terex RT Crane located at the head of NASSCO¿s Pier 12. The crane at the pier accidentally rolled on its side causing ~0.8 gallons of oil to spill onto the deck of the pier from a hydraulic hose that ruptured during the crane incident*
To safely recover the crane, NASSCO personnel disconnected a hydraulic hose in order to relieve the hydraulic oil pressure to the crane¿s boom cylinder, it was during this time at approx. 20:30 hrs,. that ~7-8 gallons of hydraulic oil was released onto the pier deck and ~1 gallon released to the San Diego Bay. NASSCO Fire, Environmental, and General Services responded and immediately started cleanup activities on the pier; however, in-water oil recovery operations could not be initiated due to low lighting. On March 10, 2021 during the follow investigation, a mixture oil and rain water was identified on the pier, a thin film oil sheen covering an area ~75ft x 120ft was also identified on the surface of the water in the San Diego Bay under and around the head of NASSCO¿s Pier 12. |
The affected area on the pier was immediately isolated to prevent traffic, NASSCO¿s General Services was dispatched to vacuum the oil/rain water mixture from the pier. US Ecology (NASSCO¿s oil spill response contractor) was dispatched to evaluate the oil on the surface of the water for recovery determination. US Ecology tested the absorbency of the oil and due to its weathering it was determined the oil could not be recovered. |
Violation |
U |
eSMR |
1088025 |
02/10/2021 |
Surface Water |
On February 10, 2021, a NASSCO Safety representative notified NASSCO Environmental that they observed construction debris (concrete, weld slag and grinding debris) going into the San Diego Bay from a construction project being performed by R.E. Staite (RES) (subcontractor to NASSCO) at Berth 7. The discharge occurred during RES jackhammering activities at the Berth 7 quay wall without secondary containment. Grinding and welding debris were also witnessed going into the Bay during the initial investigation. The incident is a prohibited discharge under NASSCO's NPDES permit. However, the discharge did not exceed a Reportable Quantity (RQ) and did not endanger health or the environment. |
The RES site supervisor immediately stopped the activities to prevent further discharge and held a stand-down with its employees. RES has developed new structural BMPs and has provided additional training to their staff. The new BMPs are strategically positioned within the work area to prevent further discharge to San Diego Bay. |
Violation |
U |
eSMR |
1086561 |
01/12/2021 |
Surface Water |
On January 12, 2021, an unknown amount of back flow of water from the launch washed onto F-Lane (between F-12 and F-14) and drained back into the Bay possibly taking NASSCO containments (industrial activity dust and particulates) with it into the bay. A light gray dust sheen was observed on surface waters, however, the dust could not be recovered as it dissipated quickly and due to the ongoing launch evolution activities. NASSCO Environmental, Facilities and General Services immediately dispatched the pump truck and began pumping the excess flood water at the F-Lane into the pump truck holding tank to prevent further discharge.
The incident is a prohibited discharge under NASSCO's NPDES permit. However, the discharge did not exceed a Reportable Quantity (RQ) and did not endanger health or the environment.
The spill was a result of the back flow from the T-AO 1 launch at WAYS 3. The flood water backwash extended beyond the expected WAYS 3 flooding areas extending to the F-Lane laydown areas that were not cleaned which resulted dust sheen. All the areas beyond WAYS 3 (adjacent laydown areas) that had the potential to flood and backwash could not be identified earlier as this was a new hull class (new ship type).
|
Based on the results of the T-AO 1 launch, a BMP plan will be developed to address the adjacent laydown areas to prevent a discharge from further launches of this class of vessel. |
Violation |
U |
eSMR |
1085125 |
12/02/2020 |
Surface Water |
December 2, 2020 at 0816 hrs. NASSCO Security was notified of an abrasive blast media discharge to the San Diego Bay from a subcontractor¿s (IMIA) abrasive blasting operation at Berth 4.
IMIA failed to install screens on their vacuum lines prior to using the vacuums to remove spent blast media from their work area. This caused trash and debris to be vacuumed into the vacuum bottle and partially obstructing the valve. IMIA employees failed to secure the valve while attempting to remove the obstruction allowing spent blast media to spill into and overflowing the secondary containment onto the pier and into San Diego Bay causing approximately a 100 ft. x 180 ft. surface dust layer. IMIA employees cleaned up the spent blast media from the pier, however; the spent blast media in the Bay could not be recovered. |
A NASSCO Corrective Action Request was issued to IMIA to prevent reoccurrence, IMIA is tasked to ensure screens are installed on their vacuum lines and instructed to cease blasting operations when faulty equipment is identified. IMIA has reviewed the incident and conducted training with all its blasting employees. |
Violation |
U |
eSMR |
1082785 |
11/17/2020 |
Surface Water |
An unknown amount of paint chips/debris and dust was spilled into the Bay when containment was removed from a sally port on the Floating Dry Dock. NASSCO Fire Department and Environmental responded and found paint chips floating in the Bay off the Port Side FWD end of the NASSCO Floater. The responsible party was identified however, material was not able to be recovered. The discharge occurred during the take down and replacement of the plastic secondary containment. The incident is a prohibited discharge under NASSCO's NPDES permit. However, the discharge did not exceed a Reportable Quantity (RQ) and did not endanger health or the environment. |
Employees were stopped from working next to water, to prevent reoccurrence, the responsible party will install dual secondary containment when working next to the water in the future. The outer containment will remain clean while the inner containment will be the primary containment to capture all the dust and debris. When the containment is removed the inner "contaminated" containment will prevent contaminants from going into the bay. |
Violation |
U |
eSMR |
1082784 |
11/06/2020 |
Surface Water |
While working on removing the cofferdam, sparks from R.E. Staite's (RES) operations were seen going into San Diego Bay. The amount of material carried to the water could not be determined. Environmental Engineering determined that, due to the material being slag from welding, it was not recoverable. The release resulted from welding operations from R.E. Staite working on the cofferdam. The incident is a prohibited discharge under NASSCO's NPDES permit. However, the discharge did not exceed a Reportable Quantity (RQ) and did not endanger health or the environment. |
Upon discovery, RES shut down work immediately and modified plans. A corrective action request was issued to the responsible party requiring them to investigate root cause and take actions to prevent recurrence. R.E.S response was received and changes implemented on 11/30/20. |
Violation |
U |
eSMR |
1080299 |
08/17/2020 |
Surface Water |
Incident Summary: On August 17, 2020, metal grinding debris was observed going into the Bay (riprap) from a facilities improvement project at Berth 8. Pacific Rim (a subcontractor to NASSCO) employees were cutting a metal space bar fence without secondary containment to prevent metal shavings from going into the riprap. NASSCO environmental engineering personnel notified the supervisor of Pacific Rim who immediately stopped the cutting activities to consult with Pacific Rim employees. The amount of metal shavings could not be estimated or recovered. The incident is a prohibited discharge under NASSCO''s NPDES permit. However, the discharge did not exceed a Reportable Quantity (RQ) and did not endanger health or the environment. |
Immediate and Corrective Actions: The Pacific Rim supervisor stopped the cutting activities as soon as he was made aware of the discharge, training was then conducted onsite and secondary containment installed. NASSCO¿s project engineer was made aware of the incident and scheduled additional training for Pacific Rim employees, the additional training was completed by NASSCO's Facilities department on 8/19/2020. |
Violation |
B |
eSMR |
1077569 |
06/26/2020 |
Surface Water |
On June 26, 2020 at 0740 hrs. approximately 30-40 grams of weld slag from torching metal cutting activities was released to San Diego Bay from a facility improvement project taking place on Pier 12. The spill was caused by a subcontractor (Casper Company) working overwater and on the pier without containment. As a result, an environmental corrective action request was issued to Caspar Company. |
Immediately after being made aware of the discharge, the contractor stopped the operations and gathered all their employees to explain the proper secondary containment requirements when conducting work over and near surface waters. Additional training on project specific BMPs was conducted by the contractor to emphasize that no work will be conducted unless containment is properly implemented. NASSCO's Fire Department and Environmental responded to the scene and determined that the material could not be recovered |
Violation |
B |
eSMR |
1071762 |
02/13/2020 |
Surface Water |
Incident 2020-017 (2/13/2020 1124): The pier coordinator for the USS Stockdale reported to NASSCO Security that approximately 10 feet of 12¿ ventilation duct fell into the Bay at Berth 3. It was also reported that the ventilation duct was immediately recovered from the Bay by the responsible party (YYK Enterprises). The ventilation duct fell in the Bay during the movement of abrasive blasting equipment on the pier. Immediate Response: The ventilation duct was immediately recovered by YYK. It was later discovered that a small amount of blast dust had been released to the Bay during the removal of the equipment from the pier; however, no cleanup actions were taken by NASSCO¿s Fire Department. Root Cause: YYK did not properly follow their procedures for removing abrasive blasting equipment. |
Preventive Actions: NASSCO Environmental met with YYK to review the incident. YYK reviewed the incident and procedure with their operators to prevent reoccurrence. |
Violation |
B |
eSMR |
1070058 |
12/07/2019 |
Surface Water |
A cable located on M/V Lurline (Matson 601), dripped a few drops of grease into San Diego Bay, causing a 1ft x 1ft surface sheen. |
Immediate / On-scene Corrective Action: The NASSCO Fire Department responded to the scene, but the sheen had already completely dissipated, and the spill was not recoverable. The cable that caused the discharge was removed, and was not able to discharge any additional material into San Diego Bay. The following agencies were notified: NRC (#1265787), CalOES (#19-7821), USCG, RWQCB. |
Violation |
B |
eSMR |
1065907 |
09/21/2019 |
Surface Water |
On September 21, 2019 at 0951 hrs, a call was made to Security to report sandblasting debris escaping through a hole in the plastic containment on the USS Higgins. Blast media was escaping from a tear in the containment. Blast media dust landed on the pier and in the bay. The Foreman and workers were able to repair the containment and clean up the material on pier with vacuums.
It was estimated that 16 ounces of sandblast dust fell in the bay creating a 3¿ x 17¿ size surface dust cloud. Due to the location of the spilled material between the ship and the pier, it was unsafe for responders to attempt the recovery of the material. |
Immediate / On-scene Corrective Action: NASSCO Fire Department arrived and notice a tear in the plastic shielding on the containment onboard the USS Higgins. By the time Fire Department arrived, work has stopped and Subcontractor were working to repair the containment and had started cleanup actions. The incident is a prohibited discharge under NASSCO's NPDES permit. However, the discharge did not exceed a Reportable Quantity (RQ) and did not endanger health or the environment.
Recommendation and Preventative Action Request: An Environmental Corrective Action (ECAR 177) was issued to the responsible Subcontractor, AMP United. The response to the ECAR is described below: Root cause: Blasting ops damaged visqueen. Watch Post lost focus on watching for breach/damage to containment. Immediate Action: Once AMPU became aware of the breach blasting operations ceased, cleaning operations in the surrounding area (containment side) and on the pier began. Containment in question was inspected and repaired where needed. AMPU safety officers and production management inspected the repairs prior to operations starting. Preventative Action: Training has been conducted by entire team on the job in question. This training covered all containment requirements set forth by AMPU. AMPU also discussed the expectation of our containment inspections (Watchmen) during operations. |
Violation |
B |
eSMR |
1065906 |
09/16/2019 |
Surface Water |
On September 16, 2019, a cylinder holding a demineralizing agent used to treat freshwater for the USS Higgins ruptured and released two gallons of freshwater and the demineralizing agent onto the pier. Residual material spilled into San Diego Bay. According to the reporting party, the cylinder was not properly closed which caused the release. The incident is a prohibited discharge under NASSCO''s NPDES permit. However, the discharge did not exceed a Reportable Quantity (RQ) and did not endanger health or the environment. |
Immediate / On-scene Corrective Action: NASSCO Fire Department was called and responded to the spill. Upon arrival, there was no residual material visible in the bay. The spill to the pier was cleaned up by Agua Air, the subcontractor responsible for the cylinder. Recommendation and Preventative Action Request: There was no further action required for this incident. |
Violation |
B |
eSMR |
1062656 |
07/05/2019 |
Surface Water |
Summary of Incident: July 5, 2019, 0345, NASSCO Security was notified of a water discharge to the San Diego Bay from between Building Ways 3 and 4. Further investigation by Environmental concluded the source of the water came from the Building Ways 4 hydrostatic relief system (groundwater). The hydrostatic PVC pipe system is located outboard along the quay-wall, a sleeve in the pipe system become disconnected or undone from the pipe causing an approx. 200 gallons of untreated hydrostatic water to discharge to the San Diego Bay. There was no discoloration or surface sheen at or within the vicinity of the discharge area. |
Immediate / On-scene Corrective Action: NASSCO Maintenance and the fire department arrived on scene and secured the discharge. Environmental was notified of the discharge and that it had been secured. A maintenance repair ticket was initiated and the system was repaired on July 5, 1210 hrs. |
Violation |
B |
eSMR |
1061616 |
06/20/2019 |
Surface Water |
On June 20, 2019 at approx. 0955 hrs., a discharge of 3-10 drops of lube oil to the San Diego Bay from the Matson 1 (Lurline) located at Berth 6 was reported to NASSCO Security. Matson 1 was preparing to take on lube oil, the intake manifold at the vessel bunker port was being tested for leaks prior to the loading however, residual oil in the system leaked a few drops to the San Diego Bay resulting in a surface sheen.
NASSCO Fire and Environmental responded to the scene, the discharge had been secured upon arrival. Consensus with Fire and Environmental not to deploy cleanup efforts as the material was very light and dissipated naturally.
An Environmental Corrective Action Request (ECAR) has been issued to Test & Trials to obtain root cause and preventive measures. |
To prevent this incident from reoccurring, the sequence for pressurizing the system will be directed towards the lube oil holding tank to capture any residual from the system during testing. |
Violation |
B |
eSMR |
Report displays most recent five years of violations. Refer to the Interactive Violation Report for more data.
|