Place ID 237327
|
|
|
|
|
|
General Information
|
Region |
Place ID |
Place Name |
Place Type |
Place Address |
Place County |
2 |
237327 |
CEMEX Construction Materials Pacific, LLC ELIOT Site |
Sand and Gravel Mining |
1544 Stanley Pleasanton, CA, 94566 |
Alameda |
|
|
Related Parties
|
|
Total Related Parties: 5
|
|
|
Regulatory Measures
|
Reg Measure ID |
Reg Measure Type |
Region |
Program |
Order No. |
WDID |
Effective Date |
Expiration Date |
Status |
Amended? |
402857 |
Enrollee - NPDES |
2 |
NPDNONMUNIPRCS |
R2-2020-0028 |
2 019135005 |
09/15/2015 |
12/31/2025 |
Active |
N |
179976 |
Enrollee |
2 |
NPDNONMUNIPRCS |
R2-2008-0011 |
2 019135001 |
06/26/2008 |
04/13/2013 |
Historical |
N |
132631 |
NPDES Permit |
2 |
NPDMINING |
R2-2003-0046 |
2 019135001 |
05/21/2003 |
05/21/2003 |
Historical |
N |
142417 |
NPDES Permit |
2 |
NPDMINING |
96-045 |
2 019135001 |
04/17/1996 |
04/17/2001 |
Historical |
N |
141901 |
NPDES Permit |
2 |
NPDMINING |
91-036 |
2 019135001 |
03/20/1991 |
03/20/1996 |
Historical |
N |
146601 |
NPDES Permit |
2 |
NPDMINING |
85-003 |
2 019135001 |
01/16/1985 |
01/16/1990 |
Historical |
N |
|
Total Reg Measures: 6
|
|
|
Violations
|
Violation ID |
Occurred Date |
Violation Type |
(-) Violation Description |
Corrective Action |
Status |
Classification |
Source |
1144020 |
04/30/2025 |
LREP |
The 2025 first quarter SMR was due on April 30 and was submitted on May 5, 2025, following a reminder email from Alessandra Moyer to Erin Cervantes. It was a report of no discharge. |
|
Violation |
B |
Report |
1127802 |
05/01/2024 |
LREP |
First quarter report was due April 30, 2024. Submitted May 14, 2024. |
|
Violation |
B |
Report |
1124787 |
02/16/2024 |
LREP |
2023 Annual Report was due on February 15, 2024, but was not submitted until February 29, 2024, after multiple email reminders. |
|
Violation |
B |
Report |
1124788 |
02/15/2024 |
Deficient Reporting |
2023 Annual Report did not contain information about violations that occurred in 2023, including unauthorized discharge in January, or late Q2, Q3, Q4, and Annual reports. Report did not include a comprehensive discussion of performance and compliance, summaries of monitoring data, wastewater facilities review and evaluation status report, annual O&MM review status report, or annual BMP Plan evaluation. |
|
Violation |
B |
Report |
1124786 |
01/31/2024 |
LREP |
Q4 2023 report was due January 30, 2024, but was not submitted until February 29, 2024, after multiple reminder emails. |
|
Violation |
B |
Report |
1122363 |
10/30/2023 |
LREP |
Quarter 3 (2023) report was due on October 30,2023, and was submitted on November 7, 2023. This is not an MMP-able violation because it is a no-discharge report. |
Report was sent after Water Board staff (AM) emailed Erin Loza to request the report on November 6, 2023. |
Violation |
B |
Report |
1119824 |
07/31/2023 |
LREP |
2023 Q2 SMR was due on July 31, 2023, but was received on September 5, 2023. It was a report of no discharge. |
Report was submitted after Regional Water Board staff requested it. |
Violation |
B |
Report |
1119769 |
01/12/2023 |
UAUTHDISC |
According to a report from CEMEX, due to an atmospheric river and related releases from the Del Valle Dam, the Arroyo Del Valle breached Lake A at the southeast corner on 1/12/2023. CEMEX staff conducted a site visit on 1/20/23, at which time they discovered that Lake A had breached the southwest corner of the lake, creating a "pass-through (outlet)" for flows. Both breaches were approximately 50 feet wide. There were also erosional escarpments to the east of the primary breach. According to CEMEX, mining has not occurred at Lake A for the past 10 years. |
Corrective Actions: "Given the ground conditions as a result of the heavy rains in January – March 2023, access to Lake A is and has been very limited. The secondary breach has cut-off vehicular access to the majority of the Lake A property. CEMEX is closely monitoring the situation and evaluating whether the continued breach of Lake A warrants emergency work to protect additional property loss. Additionally, CEMEX is pursuing an engineering evaluation and design for long-term bank stabilization repairs at the Lake A reach along the
ADV." |
Violation |
B |
Report |
Report displays most recent five years of violations. Refer to the Interactive Violation Report for more data.
|
|
Total Violations: 8
|
Priority Violations: 0
|
*Click the "(+/-) Violation Description" link to expand and contract the violation description.
*As of 5/20/2010, the Water Board's Enforcement Policy requires that all violations be classified as 1, 2 or 3, with class 1 being the highest. Prior to this, violations were simply classified as Yes or No. If a 123 classification has been assigned to a violation that occurred before this date, that classification data will be displayed instead of the Yes/No data.
|
Violation Types |
Deficient Reporting = Deficient Reporting
|
LREP = Late Report
|
UAUTHDISC = Unauthorized Discharge
|
|
|
|
Enforcement Actions
|
Enf Id |
Enf Type |
Enf Order No. |
Effective Date |
Status |
371979 |
Expedited Payment Letter |
|
|
Never Active |
456092 |
Oral Communication |
|
03/05/2024 |
Historical |
454194 |
Oral Communication |
|
08/31/2023 |
Historical |
454195 |
Oral Communication |
|
01/24/2023 |
Historical |
398756 |
Admin Civil Liability |
R2-2015-1006 |
05/12/2015 |
Historical |
373500 |
Expedited Payment Letter |
|
06/26/2008 |
Never Active |
|
Total Enf Actions: 6
|
|
|
Inspections
|
Inspection ID |
Inspection Type |
Lead Inspector |
Actual End Date |
Planned |
Violations |
Attachment |
60410290 |
B Type compliance inspection |
Alessandra Moyer |
06/19/2025 |
Y |
0 |
N/A |
32189316 |
Miscellaneous inspection |
Maya McInerney |
03/07/2018 |
N |
0 |
N/A |
18602628 |
B Type compliance inspection |
Farhad Azimzadeh |
08/28/2014 |
N |
0 |
N/A |
17567947 |
B Type compliance inspection |
Farhad Azimzadeh |
08/27/2014 |
N |
0 |
N/A |
289300 |
B Type compliance inspection |
Jenny Chen |
12/18/2001 |
Y |
0 |
N/A |
289301 |
B Type compliance inspection |
James Nusrala |
04/19/2000 |
Y |
0 |
N/A |
289298 |
B Type compliance inspection |
Vijay Patel |
08/21/1998 |
Y |
0 |
N/A |
289299 |
B Type compliance inspection |
Vijay Patel |
08/15/1996 |
Y |
0 |
N/A |
|
Total Inspections: 8 |
Last Inspection: 06/19/2025 |
|
|
|
|
 |
The current report was generated with data as of: 07/02/2025
Regional Boards are in the process of entering backlogged data.
As a result, data may be incomplete.
|
 |