[SUMMARY OF FINAL SUBMITTED VERSION]
PROGRESS REPORT BY PERMITTEE FOR
2011
Primary Owner:
SACRAMENTO MUNICIPAL UTILITY DISTRICT
Application Number:
A031596
Permit Number:
021262
Date Submitted:
2012-06-12
1. Permit Review |
I have reviewed my water right permit |
Yes
|
2. Compliance with Permit Terms and Conditions |
I am complying with all terms and conditions |
Yes
|
Description of noncompliance with terms and conditions |
|
3. Changes to the Project |
Intake location has been changed |
|
Description of intake location changes |
|
Type of use has changed |
|
Description of type of use changes |
|
Place of use has changed |
|
Description of place of use changes |
|
Other changes |
|
Description of other changes |
|
4-6. Permitted Project Status |
Project Status |
Not Complete
|
6a. Construction work has commenced |
Yes
|
6b. Construction is completed |
Yes
|
6c. Beneficial uses of water has commenced |
Yes
|
6d. Project will be completed within the time period specified in the permit |
Yes
|
6e. Explanation of work remaining to be done |
The order approving the issuance of the permit contains the rationale for continuing. |
6f. Estimated date of completion |
12/31/2040 |
7. Purpose of Use
|
Power |
559
MW
|
Recreational |
Boating, fishing, water contact sport
|
8. Amount of Water Diverted and Used |
Month |
Amount directly diverted or
collected to storage
(Acre-Feet)
|
Amount used
(Acre-Feet)
|
January |
934 |
23 |
February |
108 |
591 |
March |
3950 |
166 |
April |
1085 |
729 |
May |
54 |
10 |
June |
844 |
40 |
July |
68 |
3056 |
August |
847 |
1160 |
September |
282 |
68 |
October |
2820 |
4856 |
November |
1153 |
363 |
December |
3391 |
585 |
Total |
15536 |
11647 |
9. Maximum Rate of Diversion for each Month |
Month |
Maximum Rate of Diversion
()
|
January |
|
February |
|
March |
|
April |
|
May |
|
June |
|
July |
|
August |
|
September |
|
October |
|
November |
|
December |
|
10. Storage |
Reservoir name |
Spilled this year |
Feet below spillway at maximum storage |
Completely emptied |
Feet below spillway at minimum storage |
Method used to measure water level |
Junction |
Yes
|
|
No
|
29 |
pressure transducer |
Camino |
Yes
|
|
No
|
43 |
incremental level encoder |
Brush Creek |
Yes
|
|
No
|
15 |
pressure transducer |
Slab Creek |
Yes
|
|
No
|
25 |
incremental level encoder |
Conservation of Water |
11. Are you now employing water conservation efforts? |
|
Description of water conservation efforts |
|
12. Amount of water conserved |
|
Water Quality and Wastewater Reclamation |
13. During the period covered by this Report, did you use reclaimed water
from a wastewater treatment facility, water from a desalination facility,
or water polluted by waste to a degree which unreasonably affects the
water for other beneficial uses?
|
|
14. Amount of reclaimed, desalinated, or polluted water used |
|
Conjuctive Use of Groundwater and Surface Water |
15. During the period covered by this Report, were you using groundwater
in lieu of available surface water authorized under your permit?
|
|
16. Amounts of groundwater used |
|
Additional Remarks |
(5a, 5b) These figures only include the quantity of water directly diverted and withdrawn from storage for power generation. All water placed into storage is also beneficially used for recreation, whether withdrawn from storage or not.
|
Attachments |
File Name |
Description |
Size |
No Attachments |
Contact Information of the Person Submitting the Form |
First Name |
Dudley |
Last Name |
McFadden |
Relation to Water Right |
Authorized Official |
Has read the form and agrees the information in the report is true to the best of his/her knowledge and belief |
Yes
|